○○○○년도

○○~○○ 고속도로 건설공사

기본 및 실시설계용역 제○공구

BIM 전면설계 과업내용서

(Terms of Reference)

한국도로공사

목 차

제1장 일반 사항

제1절 과 업 명 ····························································································································1

제2절 과업의 목적 ······················································································································1

제3절 과업의 구간 및 범위 ·····································································································1

제4절 과업의 개요 ······················································································································2

제5절 과업의 수행기간 ·············································································································3

제6절 설계변경조건 ···················································································································3

제7절 주요업무의 사전협의 등 ·······························································································3

제8절 과업수행 및 공정보고 ···································································································4

제9절 용역감독 등 ······················································································································5

제10절 자료요구·질의 등 ··········································································································6

제11절 계약상대자의 책임 ·······································································································6

제12절 적용규정 및 설계기준 ·································································································7

제13절 관계기관 협의 및 인·허가 ·························································································7

제14절 건설기술진흥법령의 준수 ···························································································7

제15절 보안 및 비밀유지 ·········································································································8

제16절 용어의 해석 ···················································································································9

제17절 용역수행자의 교체 ·······································································································9

제18절 설계 시 고려되어야 할 사항 ·····················································································9

제19절 신기술의 도입 ·············································································································10

제20절 토석정보공유시스템의 활용 ·····················································································10

제21절 작업분류체계(WBS) 자료 제출 ··············································································10

제22절 건설공사 물량내역수정입찰 관련 사항 ································································10

제23절 건설공사의 공사기간 산정 ·······················································································11

제24절 기타 사항 ······················································································································11

제2장 인력운영

제1절 인력 투입계획 ···············································································································12

제2절 핵심전문가 책임 및 의무 ···························································································14

참조 1. 조사업무 세부절차

제1절 관련계획 조사 및 검토 ·······························································································19

제2절 현지조사 및 답사 ·········································································································19

제3절 수리․수문조사 ·············································································································20

제4절 환경영향조사 ·················································································································20

제5절 측량 ··································································································································20

제6절 지질 및 지반조사 ·········································································································21

제7절 지장물 및 구조물조사 ·································································································21

제8절 용지조사 ··························································································································22

제9절 BIM 데이터 작성 ·········································································································23

참조 2. 계획업무 세부절차

제1절 전 단계 성과검토 ·········································································································24

제2절 관련규정의 적용 ···········································································································24

제3절 교통 분석 및 평가 ·······································································································25

제4절 환경영향 검토 및 평가 ·······························································································27

제5절 재해영향평가 검토 ·······································································································27

제6절 노선선정 ··························································································································27

제7절 수리·수문 검토 ··············································································································29

제8절 구조물계획 ······················································································································30

제9절 설계기준 작성 및 기타 ·······························································································32

제10절 관계기관 협의 및 민원 검토 ···················································································33

참조 3. 상세설계 업무 세부절차

제1절 설계조건 ··························································································································34

제2절 선형설계 ··························································································································35

제3절 토공설계 ··························································································································35

제4절 용·배수공 설계 및 횡단구조물 설계 ·······································································37

제5절 소구조물공 설계 ···········································································································38

제6절 포장공 설계 ···················································································································38

제7절 출입시설 및 부대시설 설계 ·······················································································39

제8절 교량설계 ··························································································································41

제9절 터널설계 ··························································································································45

제10절 가설구조물 설계 ·········································································································49

제11절 계측계획 및 기타 ·······································································································49

제12절 토석정보공유시스템(TOCYCLE)의 활용 ·····························································49

제13절 건설안전을 고려한 설계(Design For Safety) ··················································50

제14절 설계단계 재난예방진단(DPA) 시행 ······································································50

제15절 산업재해 예방을 위한 안전보건대장 작성 ··························································51

제16절 기타사항 ························································································································51

참조 4. 설계도서 작성기준

제1절 성과품의 구분 ···············································································································53

제2절 성과품의 내용 ···············································································································53

제3절 성과품 작성의 특기사항 ·····························································································61

제4절 인·허가 도서 작성 ········································································································69

제5절 기타사항 ··························································································································70

제6절 설계도서 작성 및 납품기준 ·······················································································70

제7절 BIM 성과품 품질 관리 ·······························································································72

첨부 #1. 비밀보장의 의무 시행사항

1. 용역업체 보안 준수사항 ····································································································79

2. 시행방법 ·································································································································79

첨부 #2. 용지 및 지장물 현황조서 작성요령

1. 용지현황조서 ·························································································································81

2. 지장물 현황조서 ··················································································································81

-별지서식-

서식#1-1, 2 보안각서

서식#2 작업일지

서식#3 민원사항

서식#4 관계기관 협의사항

서식#5 분야별 참여기술인 명단

서식#6 설계현황

서식#7 설계대장

서식#8 교량대장

서식#9 터널대장

번호 제목 글쓴이 날짜 조회 수
공지 한국도로공사_기준_자료목록 입니다 황대장 2021.05.18 20261
공지 한국도로공사_방침_자료목록 입니다 황대장 2021.05.18 12941
공지 한국도로공사_지침_자료목록 입니다 황대장 2021.05.18 17606
375 201509_공사시방서(1)제10장 시멘트콘크리트 포장공사 file 효선 2023.05.12 1515
374 201509_공사시방서(1)제11장 안전시설공사 file 효선 2023.05.12 784
373 201509_공사시방서(1)제12장 환경관리 및 부대공사 file 효선 2023.05.11 820
372 201509_공사시방서(1)제13장1편_재료 file 효선 2023.05.11 840
371 201509_공사시방서(1)제13장2편_재료 file 효선 2023.04.24 763
370 201509_공사시방서(1)제13장3편_재료 file 효선 2023.04.20 770
369 201509_공사시방서(2)-광주순환 2공구(1022)지반구조취합_제0편목차 file 효선 2023.04.20 834
368 201509_공사시방서(2)-광주순환 2공구(1022)지반구조취합_제1편 file 효선 2023.04.20 812
367 201509_공사시방서(2)-광주순환 2공구(1022)지반구조취합_제2편 file 효선 2023.04.20 832
366 201509_공사시방서(2)-광주순환 2공구(1022)지반구조취합_제3편 file 효선 2023.04.19 848
365 201509_공사시방서(2)-광주순환 2공구(1022)지반구조취합_제4편 file 효선 2023.04.07 792
364 198903_배수구조물설계법(기록보관용) file 사이트관리자 2023.02.18 961
363 201608_저토피 지중구조물 상부 포장파손 저감방안 file 효선 2022.12.21 827
362 202106_하이패스나들목 설계지침 제정(본문) file 효선 2022.11.25 1231
361 고속도로스마트설계지침(2020.9)_목차 file 땅콩 2021.08.30 933
360 고속도로스마트설계지침(2020.9)_1장_일반사항 file 땅콩 2021.08.30 1033
359 고속도로스마트설계지침(2020.9)_2장_기본사항 file 땅콩 2021.08.30 1192
358 고속도로스마트설계지침(2020.9)_3장_BIM전면설계기준 file 땅콩 2021.08.30 4327
357 고속도로스마트설계지침(2020.9)_4장_스마트설계지침 file 땅콩 2021.08.30 998
» 고속도로스마트설계지침(2020.9)_부속서_1_BIM전면설계_과업내용서표준(안)_목차 file 땅콩 2021.08.30 918