/ 제 3 장 /

단가산출요령

1. 토공 ···································································································· 829

2. 비탈면공 ····························································································· 875

3. 배수공 ································································································ 891

4. 구조물공 ····························································································· 955

5. 지하차도공 ························································································· 992

6. 터널공 ································································································ 998

7. 포장공 ······························································································ 1019

8. 교통안전시설공 ················································································ 1040

9. 부대공 ······························································································ 1060

 

- 829 -

1 토공

번 호 공 종 단 위 단 가 기 준 비 고

1.01

a

a-1

기존구조물 깨기

무근콘크리트 깨기

무근콘크리트

(T=30cm 미만)

㎥ 1. 깨 기

1) 기 계 (100%)

① 대형브레이커+굴삭기 (0.7㎥)

Q=(3.3+5.9)/2=4.6㎥/m

② 작업보조원

- 보통인부 1인

③ 치즐소모량 (0.7㎥용)

- 0.01본/hr

2. 집토 (굴삭기 1.0㎥)

q= 1.0, k=0.55, f=1/1.50, E=0.35, Cm=21sec

Q=3600×q×k×f×E/Cm= ㎥/hr

※ 적사 및 운반은 건설폐기물 파쇄, 또는 폐기물 상차및 운반비에서 적용

「건설표준품셈 공통부문

8-2-15 대형브레이커」 참조

「건설표준품셈 공통부문

8-2-3 굴삭기」 참조

a-2 무근콘크리트

(T=30cm 이상)

㎥ 1. 깨 기

1) 기 계 (100%)

① 대형브레이커+굴삭기 (0.7㎥)

Q=(2.6+4.6)/2=3.60㎥/hr

② 작업보조원

- 보통인부 1인

③ 치즐소모량 (0.7㎥용)

- 0.01본/hr

2. 집토 (굴삭기 1.0㎥)

q= 1.0, k=0.55, f=1/1.50, E=0.35, Cm=21sec

Q=3600×q×k×f×E/Cm= ㎥/hr

※ 적사및 운반은 건설폐기물 파쇄, 또는 폐기물 상차및 운반비에서 적용

「건설표준품셈 공통부문

8-2-15 대형브레이커」 참조

「건설표준품셈 공통부문

8-2-3 굴삭기」 참조

- 830 -

번 호 공 종 단 위 단 가 기 준 비 고

b

b-1

철근콘크리트 깨기

철근 콘크리트

(T=30cm 미만)

㎥ 1. 깨 기

1) 기 계 (100%)

① 대형브레이커+굴삭기 (0.7m3)

Q=(1.6+3.3)/2=2.45m3/m

② 작업보조원

- 보통인부 1인

③ 치즐소모량 (0.7m3용)

- 0.01본/hr

2. 철근절단

- 용 접 공 : 0.02인

- 보통인부 : 0.08인

- 아세칠렌 : 0.05kg

- 산 소 : 135L

3. 집토 (굴삭기 1.0m3)

q= 1.0, k=0.55, f=1/1.50, E=0.35, Cm=21sec

Q=3600×q×k×f×E/Cm= m3/hr

※ 적사및 운반은 건설폐기물 파쇄, 또는 폐기물 상차및 운반비에서 적용

4. 고철공제

A=1㎥ ×0.008×7,850kkg/㎥ ×80%=50.24 kg/m3 ≒ 50 kg/m3

「건설표준품셈 공통부문

8-2-15 대형브레이커」 참조

단가기준에 나와있는 스타일로

일괄 변경

이후 메모 변경

「건설표준품셈 건축부문

제12장 유지보수공사

12-3-2 콘크리트 구조물헐기」

참조

「건설표준품셈 공통부문

8-2-3 굴삭기」 참조

- 831 -

번 호 공 종 단 위 단 가 기 준 비 고

b-2 철근 콘크리트

(T=30cm 이상)

㎥ 1. 깨 기

1) 기 계

① 대형브레이커+굴삭기 (0.7m3)

Q=(1.4+2.7)/2=2.05m3/m

② 작업보조원

- 보통인부 1인

③ 치즐소모량(0.7m3용)

- 0.01본/hr

2. 철근절단

- 용 접 공 : 0.02인

- 보통인부 : 0.08인

- 아세칠렌 : 0.05kg

- 산 소 : 135L

3. 집토 (굴삭기 1.0m3)

q= 1.0, k=0.55, f=1/1.50, E=0.35, Cm=21sec

Q=3600×q×k×f×E/Cm= m3/hr

※ 적사및 운반은 건설폐기물 파쇄, 또는 폐기물 상차및 운반비에서 적용

4. 고철공제

A=1㎥ ×0.008×7,850kkg/㎥ ×80%=50.24 kg/m3 ≒ 50 kg/m3

「건설표준품셈 공통부문

8-2-15 대형브레이커」참조

「건설표준품셈 건축부문

제12장 유지보수공사

12-3-2 콘크리트 구조물헐기」

참조

「건설표준품셈 공통부문

8-2-3 굴삭기」 참조

c

c-1

석축헐기

석축헐기(찰쌓기) ㎡ 1. 인력철거

- 보통인부 : 0.6인

2. 잡재료비 (인력품의 5%)

3. 소 운 반 (리어카 L=20m)

Rt=(132+264+340)/3=245.33kg/m2

L=20m, V=2500, t1=5, T=450시간

N=V×T/(120×L+V×t1)= 회/인

Q=(N×250)/Rt= m2/인

- 보통인부 : 2인

「건설표준품셈 건축부문

12-3-4 석축 벽돌 헐기 및 콘

크리트 부수기」 참조

※ 유용할 경우만 적용

- 832 -

번 호 공 종 단 위 단 가 기 준 비 고

c-2 석축헐기(메쌓기) ㎡ 1. 인력철거

- 보통인부 (뒷길이 60cm 이내) : 0.2인

- 보통인부 (뒷길이 60cm 이상) : 0.3인

2. 잡재료비 (인력품의 5%)

3. 소 운 반 (리어카 L=20m)

Rt=(132+264+340)/3=245.33kg/㎡

L=20m, V=2500, t1=5, T=450시간

N=V×T/(120×L+V×t1)= 회/인

Q=(N×250)/Rt= ㎡/인

- 보통인부 : 2인

「건설표준품셈 건축부문

12-3-4 석축 벽돌 헐기 및 콘

크리트 부수기」 참조

※ 유용할 경우만 적용

d

d-1

기존포장 깨기

콘크리트 (기계) ㎥ 1. 기계 깨기

1) 깨기 (대형브레이커+굴삭기 (0.7㎥))

Q=(3.3+5.9)/2=4.6㎥/hr

2) 치즐소모량 (0.7㎥용)

0.01본/hr

3) 작업보조원

- 보통인부 : 1인

2. 집토 (굴삭기 1.0㎥)

q= 1.0, k=0.55, f=1/1.50, E=0.35, Cm=21sec

Q=3600×q×k×f×E/Cm= ㎥/hr

※ 적사및 운반은 건설폐기물 파쇄, 또는 폐기물 상차및 운반비에서 적용

「건설표준품셈 공통부문

8-2-15 대형브레이커」 참조

「건설표준품셈 공통부문

8-2-3 굴삭기」 참조

d-2 아스팔트 (기계) ㎥ 1. 기계 깨기

1) 깨기 (대형브레이커+ 굴삭기 (0.7㎥))

Q=16.5㎥/hr(아스콘 포장 30cm 미만), 12.5㎥/hr(아스콘 포장 30cm 이상)

2) 치즐소모량 (0.7㎥용)

0.01본/hr

3) 작업보조원

- 보통인부 : 1인

「건설표준품셈 공통부문

8-2-15 대형브레이커 헐기」

참조

- 833 -

번 호 공 종 단 위 단 가 기 준 비 고

2. 집토 (굴삭기 1.0㎥)

q= 1.0, k=0.55, f=1/1.50, E=0.35, Cm=21sec

Q=3600×q×k×f×E/Cm= ㎥/hr

※ 적사및 운반은 건설폐기물 파쇄, 또는 폐기물 상차및 운반비에서 적용

「건설표준품셈 공통부문

8-2-3 굴삭기」 참조

d-3 보도블럭 포장헐기 ㎡ 1. 인력철거

-설치품의 50%

1) 시공량 : 소형고압블록 A=300㎡/일, 대형블록 A=270㎡/일, 보도용콘크리트블록

A=370㎡/일

2) 특별인부 2인/일

보통인부 4인/일

3) 플레이트콤팩터(1.5ton) 1대/일

굴삭기(0.6㎥) 1대/일

4) 잡재료비(인력품의 5%)

5) 공구손료(인력품의 3%)

2.소운반(리어카) L=20m

t1=5, V=2500, T=450, L=20m

N=V×T/(120×L+V×t1)= 회/인

Q=N×250kg/2300kg/㎥÷T(두께) = ㎡/인

- 보통인부 : 2인

「건설표준품셈 토목부문

1-11-20 보도용 블록 포장 철

거」 참조

e

e-1

포장절단

콘크리트(기계) m 1. 운전경비

1) 블레이드 (D=320~400mm, T=3.2mm 기준) 0.0031개

2) 보통인부 1인/일

특별인부 1인/일

3) 물운반

L=0.1km, V=2.5km/hr

N=(2500×450)/(120×100+2500×4)= 회/일

Q=N×250/1000= ℓ/일

- 보통인부 : 2인

「건설표준품셈 토목부문

1-7-1 콘크리트포장 절단」

참조

- 834 -

번 호 공 종 단 위 단 가 기 준 비 고

2. 기계사용료

1) 콘크리트 컷트 (320~40mm)

Q=60m/일

2) 동력분무기 (4.85kw) 0.5대/일

e-2 아스팔트(기계) m 1. 운전경비

1) 블레이드 (D=320~400mm, T=3.2mm 기준) 0.0027개

2) 보통인부 1인/일

특별인부 1인/일

3) 물운반

L=0.1km, V=2.5km/hr

N=(2500×450)/(120×100+2500×4)= 회/일

Q=N×250/1000= ℓ/일

- 보통인부 : 2인

2. 기계사용료

1) 콘크리트 컷트 (320~40mm)

Q=60m/일

2) 동력분무기 (4.85kw) 0.5대/일

「건설표준품셈 토목부문

1-7-2 아스콘포장 절단」

참조

f 호안블록 헐기 ㎡ ※ 가설비의 50% 적용

1. 크레인 10Ton : 0.048hr

2. 인력품

특별인부 : 0.017인, 보통인부 : 0.007인

「건설표준품셈 토목부문

2-3-3 블록 붙이기(기계)」

참조

g 돌망태 헐기 ㎡ ※ 가설비의 50% 적용

제1장 굴삭기 1.0㎥ : 0.030hr

제2장 인력품

석공 : 0.044인, 특별인부 : 0.014인, 보통인부 : 0.006인

「건설표준품셈 토목부문

2-2-1 타원형 돌망태 설치」

참조

h 가드레일 철거 m ※ 교통안전시설공 8.04 가드레일 설치비의 50% 적용

가드레일 일반구간, 단부, 중앙분리대구간으로 구분

「건설표준품셈 토목부문

1-11-21 가드레일 철거」

참조

i 강교철거 ton ※ 가설비의 50% 적용

1. 크레인 100Ton(무한궤도) : 2대

2. 인력품

특별인부 : 8인, 보통인부 : 6인

3. 콘크리트깨기 : 별도계상

- 835 -

번 호 공 종 단 위 단 가 기 준 비 고

j P.S.C Beam 철거 본

k 건설폐기물 파쇄 ㎥ 1. 콘크리트 및 아스콘깨기 : 별도계상

2. 적 재 : 타이어 페이로더 2.87m3

q0=2.87, K=0.55, f=1/1.50, E0=0.35

m=1.8, L=8m, t1=9, t2=14

cm=(m×L)+t1+t2= sec

Q1=3600×q0×K×f×E0/cm= m3/hr

3. 운 반 (덤프 15TON+자동덮개)

L=공사연장/4, E=0.9, f=1/1.50

q1=15/2.3 ×1.50 =

n=q1/(2.87×K)= 회

T1=(cm×n)/(60×E0)= 분

T2=(L/15+L/20)×60= 분

T3=0.8, T4=0.42분, T5=0.5, T6=1.5

cm=T1+T2+T3+T4+T5+T6= 분

Q=60×q1×f×E/cm= m3/hr

4. 크라샤투입 : 타이어페이로더 2.87m3

q = 2.87 , f=1.0 , K=0.55 , E=0.35 , T1=9, T2=14

Cm=1.8×20+T1+T2 = sec

Q=3600×q×K×f×E/Cm = m3/hr

3. 크라싱(이동식크라샤150TON)

Qc= 273 ton/hr , E=0.40

Qp2=Qc×E = ton/hr

Q = Qp2/2.3ton/hr = m3/hr

「건설표준품셈 공통부문

8-2-5 로더」 참조

「건설표준품셈 공통부문

8-2-8 덤프트럭」 참조

「건설표준품셈 공통부문

8-2-14 크러셔」 참조

1.02 측구 뚝쌓기

(인력)

㎥ 1. 인력품

보통인부 : 0.11인

「건설표준품셈 공통부문

3-2-1 인력 흙 다지기」 참조

- 836 -

번 호 공 종 단 위 단 가 기 준 비 고

1.03

a

표토제거

답구간 ㎡ 1. 도 쟈 (19TON)

T=0.2m, D=20m E=0.55, e=0.96, f=1/1.3

V1=40m/분, V2=46m/분

q0=3.2×e=

cm=D/V1+D/V2+0.25=

Q1=60×q0×f×E/cm= m3/hr

Q=Q1/T= m2/hr

「건설표준품셈 공통부문

8-2-1 불도저」 참조

* 표토제거

T=0.2m

b 답외구간 ㎡ 1. 도 쟈 (32TON)

T=0.2m, D=20m, E=0.65, e=0.96, f=1/1.3

V1=40m/분, V2=43m/분

q0=5.5×e=

cm=D/V1+D/V2+0.25=

Q1=60×q0×f×E/cm= m3/hr

Q=Q1/T= m2/hr

「건설표준품셈 공통부문

8-2-1불도저」 참조

* 표토제거

T=0.2m

c 비옥토 수거 1. 도 쟈 (32TON)

T=0.2m, D=20m, E=0.65, e=0.96, f=1/1.3

V1=40m/분, V2=43m/분

q0=5.5×e=

cm=D/V1+D/V2+0.25=

Q1=60×q0×f×E/cm= ㎥/hr

Q=Q1/T= ㎡/hr

「건설표준품셈 공통부문

8-2-1 불도저」 참조

* 비옥토 수거

T=0.2m

1.04

a

a-1

벌개제근 및 가로수 제거

벌개제근(벌목비포함)

뿌리뽑기 ㎡

∘ 입목본수도 : 50~60% ∘ 수 경 : 10~20cm ∘ 수 종 : (침엽+잡목+활엽)/3 ∘ 집재거리는 100m기준, 이를 초과하는 경우 100m 증가마다 인력품 30%씩 가산

1. 노무비

1) 보통인부 : 0.00106인

2. 집재(굴삭기+부착용집게 0.2㎥)

Q=0.00376hr/㎥

「건설표준품셈 공통부문

3-7-2 뿌리뽑기」 참조

- 837 -

번 호 공 종 단 위 단 가 기 준 비 고

a-2 벌목 ㎡ ∘ 나무높이 : 5m이상~8m미만 ∘ 집재거리는 100m기준, 이를 초과하는 경우 100m 증가마다 인력품 30%씩 가산

1. 노무비

1) 벌 목 부 : 0.00280인

2) 보통인부 : 0.00066인

2. 공구손료 및 경장비(인력품의 10%)

3. 집재(굴삭기+부착용집게 0.2㎥)

Q=0.00354hr/㎥

「건설표준품셈 공통부문

3-7-1벌목」 참조

b 가로수 제거 본 1. 가로수 제거 (굴삭기 0.7㎥)

소요시간 15분/본 (평균이동거리 10m 포함)

Q=60/15= 본/hr

2. 보통인부 : 1인×15분/450= 인

3. 운 반 (덤프트럭 15TON)

q=4.9×2.2×0.94= ㎥/대

k=0.9, N=q/0.7= 본/대, L=2km

t1=2.96×14= 분, t2=(L/15+L/20)×60= 분

t3=0.8, t4=0.42

cm=t1+t2+t3+t4=

Q1=60×q×k/cm= ㎥/hr

Q2=Q1/0.7= 본/hr

4. 뿌리제거(폐기물 처리비) : 부대공 일괄적용

「건설표준품셈 공통부문

8-2-3 굴삭기」 참조

「건설표준품셈 공통부문

8-2-8 덤프트럭」 참조

1.05

a a-1

흙깎기

토사

토사(도쟈 19TON) ㎥ 1. 깎 기

1) 도쟈 (19TON) : 공사규모가 적고, 흙의 성질이 약한 것

L=20m, f=1/1.30, E=0.60, V1=40, V2=46

q0=3.2, e=0.96, q=q0×e=

cm=L/V1+L/V2+0.25= 분

Q=60×q×f×E/cm= ㎥/hr

「건설표준품셈 공통부문

8-2-1 불도저」 참조

a-2 토사(도쟈 32TON) ㎥ 1) 도쟈 (32TON) : 공사규모가 크고, 흙의 성질이 단단한 것

L=20m, f=1/1.30, E=0.60, V1=40, V2=43

q0=5.5, e=0.96, q=q0×e=

cm=L/V1+L/V2+0.25=

Q=60×q×f×E/cm= ㎥/hr

「건설표준품셈 공통부문

8-2-1 불도저」 참조

- 838 -

번 호 공 종 단 위 단 가 기 준 비 고

b 리핑암 ㎥ 1. 깎 기

1) 리퍼도쟈 (리퍼2본 + 도쟈 32TON)

L=15m, An=0.4, f=1,

E0=(0.7+0.5+0.4)/3=0.53

cm=0.05×L+0.25= 분

Q=60×An×L×f×E0/cm= ㎥/hr

2) 집 토 (도쟈 32TON)

L=20m, q0=5.5, e=0.96, f=1/1.35 (1.3~1.35)

E=0.48, V1=40, V2=43, q=q0×e=

cm=L/V1+L/V2+0.25=

Q=60×q×f×E/cm= ㎥/hr

「건설표준품셈 공통부문

8-2-2 리퍼」 참조

「건설표준품셈 공통부문

8-2-1 불도저」 참조

c

c-1

발파암 깎기

브레이커(기계) ㎥ 브레이커 90% +발파 10%

1. 암석 절취(10%)

1) 암석절취

① 폭약 : 0.35kg

② 뇌관 : 1.0EA

③ 비트 : 0.008EA

④ 화약취급공 : 0.041인

⑤ 보통인부 : 0.103인

⑥ 착암공 : 0.041인

2) 기계사용료 : 편절암 참조

① 소형브레이커(2.7㎥/min) : 0.203 hr

② 공기압축기(10.3㎥/min) : 0.074 hr

2. 깎 기(90%)

1) 대형브레이커 + 굴삭기 (0.7㎥) ∙(연암+보통암+경암)/3×0.9=

2) 치즐소모량 (0.7㎥) : 0.018본/hr×0.9

3. 집 토 (도쟈 32TON)

L=20m, f=1/1.625, E=0.25, q1=5.5, H=0.96

V1=40, V2=43, q0=q1×H=

cm=L/V1+L/V2+0.25=

Q=60×q0×f×E/cm= ㎥/hr

「건설표준품셈 공통부문

3-1-11 암발파(소형브레이커)」

참조

「건설표준품셈 공통부문

8-2-15 대형브레이커」 참조

「건설표준품셈 공통부문

8-2-1 불도저」 참조

- 839 -

번 호 공 종 단 위 단 가 기 준 비 고

c-2 소형브레이커 ㎥ 1. 재료비

1) 폭약 : 0.35kg

2) 뇌관 : 1.0EA

3) 비트 : 0.008EA

2. 노무비

1) 화약취급공 : 0.0041인

2) 착 암 공 : 0.041인

3) 보통인부 : 0.103인

3. 기계경비

1) 소형브레이커(2.7㎥/min)

Q=0.203hr/㎥

2) 에어호스(1.91cm)

Q=0.203hr/㎥

3) 공기압축기(10.3㎥/min)

Q=0.074hr/㎥

4. 집토(도쟈 32TON)

L=20m, f=1/1.625, E=0.25, q1=5.5, e=0.96

V1=40, V2=43, q0=q1×e=

cm=L/V1+L/V2+0.25=

Q=60×q0×f×E/cm= ㎥/hr

「건설표준품셈 공통부문

3-1-11 암발파(소형브레이커)」

참조

「건설표준품셈 공통부문

8-2-15 대형브레이커」 참조

「건설표준품셈 공통부문

8-2-1 불도저」 참조

- 840 -

번 호 공 종 단 위 단 가 기 준 비 고

d

d-1

미진동 굴착공법

미진동굴착

(TYPE-1)

m3 1. 재료비

1) 미진동파쇄제 : 0.313kg

2) 잡재료비 (주재료비의 5%)

2. 노무비

1) 화약취급공 : 0.040인

2) 보통인부 : 0.060인

3. 기계경비

1) 유압식 크로울러드릴(110kW)

Q=0.100hr/㎥

소모자재(비트, 로드, 생크로드, 슬리브) : 기계경비의 24%

2) 굴삭기(1.0㎥)+대형브레이커(2차 파쇄)

Q=0.040hr/㎥

소모자재(치즐) : 기계경비의 5%

4. 발파 보호공

1) 보통인부 : 0.125인/회

2) 굴삭기(1.0㎥) : 1.0hr/회

3) 보호매트의 재료비는 별도 계상

5. 집토(도쟈 32TON)

L=20m, f=1/1.625, E=0.35, q1=5.5, e=0.96

V1=40, V2=43, q0=q1×e=

cm=L/V1+L/V2+0.25=

Q=60×q0×f×E/cm= ㎥/hr

「건설표준품셈 공통부문

3-1-5 암발파(미진동굴착

TYPE-Ⅰ)」 참조

- 841 -

번 호 공 종 단 위 단 가 기 준 비 고

d-2 유압식 할암공법 ㎥ 1. 재료비

1) 유압할암봉 : 0.022개

2. 노무비

1) 기계설비공 : 0.068인

2) 특별인부 : 0.271인

3. 기계경비

1) 유압식 크로울러드릴(110kW)

Q=0.121hr/㎥

소모자재(비트, 로드, 생크로드, 슬리브) : 기계경비의 24%

2) 발전기(25kW)

Q=0.486hr/㎥

3) 유압식 할암기(Ø80mm)

Q=0.486hr/㎥

4) 굴삭기+대형브레이커(2차 파쇄)

Q=0.121hr/㎥

소모자재(치즐) : 기계경비의 2%

4. 발파 보호공

1) 보통인부 : 0.125인/회

2) 굴삭기(1.0㎥) : 1.0hr/회

3) 보호매트의 재료비는 별도 계상한다.

5. 집토(도쟈 32TON)

L=20m, f=1/1.625, E=0.35, q1=5.5, e=0.96

V1=40, V2=43, q0=q1×e=

cm=L/V1+L/V2+0.25=

Q=60×q0×f×E/cm= ㎥/hr

「건설표준품셈 공통부문

3-1-4 암파쇄(유압식 할암공법

」 참조

- 842 -

번 호 공 종 단 위 단 가 기 준 비 고

e 정밀진동제어발파

(TYPE-Ⅱ)

㎥ 1. 재료비

1) 폭약(D=25mm) : 0.25kg

2) 전기뇌관(L=3.5m) : 0.99EA

3) 잡재료비(발파선, 전색재료 등) : 재료비의 5%

2. 노무비

1) 화약취급공 : 0.023인

2) 보통인부 : 0.032인

3. 기계경비

1) 유압식 크로울러드릴(110kW)

Q=0.080hr/㎥

소모자재(비트, 로드, 생크로드, 슬리브) : 기계경비의 24%

2) 굴삭기+대형브레이커(2차 파쇄)

Q=0.025hr/㎥

소모자재(치즐) : 기계경비의 5%

4. 발파 보호공

1) 보통인부 : 0.125인/회

2) 굴삭기(1.0㎥) : 1.0hr/회

3) 보호매트의 재료비는 별도 계상한다.

5. 집토(도쟈 32TON)

L=20m, f=1/1.625, E=0.35, q1=5.5, e=0.96

V1=40, V2=43, q0=q1×e=

cm=L/V1+L/V2+0.25=

Q=60×q0×f×E/cm= ㎥/hr

「건설표준품셈 공통부문

3-1-6 암발파(정밀진동제어발

파 TYPE-Ⅱ)」 참조

- 843 -

번 호 공 종 단 위 단 가 기 준 비 고

f f-1

진동제어발파

진동제어(소규모)발파

(TYPE-Ⅲ)

㎥ 1. 재료비

1) 폭약(D=32mm) : 0.35kg

2) 전기뇌관(L=3.5m) : 0.35EA

3) 잡재료비(발파선, 전색재료 등) : 재료비의 5%

2. 노무비

1) 화약취급공 : 0.012인

2) 보통인부 : 0.017인

3. 기계경비

1) 유압식 크로울러드릴(110kW)

Q=0.049hr/㎥

소모자재(비트, 로드, 생크로드, 슬리브) : 기계경비의 24%

2) 굴삭기

Q=0.013hr/㎥

4. 발파 보호공

1) 보통인부 : 0.125인/회

2) 굴삭기(1.0㎥) : 1.0hr/회

3) 보호매트의 재료비는 별도 계상한다.

5. 집토(도쟈 32TON)

L=20m, f=1/1.625, E=0.35, q1=5.5, e=0.96

V1=40, V2=43, q0=q1×e=

cm=L/V1+L/V2+0.25=

Q=60×q0×f×E/cm= ㎥/hr

「건설표준품셈 공통부문

3-1-7 암발파(소규모진동제어

발파 TYPE-Ⅲ)」 참조

- 844 -

번 호 공 종 단 위 단 가 기 준 비 고

f-2 진동제어(중규모)발파

(TYPE-Ⅳ)

㎥ 1. 재료비

1) 폭약(D=32mm) : 0.33kg

2) 전기뇌관(각선길이, L=4.5m) : 0.11EA

3) 잡재료비(발파선, 전색재료 등) : 재료비의 5%

2. 노무비

1) 화약취급공 : 0.007인

2) 보통인부 : 0.009인

3. 기계경비

1) 유압식 크로울러드릴(110kW)

Q=0.021hr/㎥

소모자재(비트, 로드, 생크로드, 슬리브) : 기계경비의 24%

2) 굴삭기

Q=0.009hr/㎥

4. 발파 보호공

1) 보통인부 : 0.125인/회

2) 굴삭기(1.0㎥) : 1.0hr/회

3) 보호매트의 재료비는 별도 계상한다.

「건설표준품셈 공통부문

3-1-8 암발파(중규모진동제어

발파 TYPE-Ⅳ)」 참조

- 845 -

번 호 공 종 단 위 단 가 기 준 비 고

g 일반발파

(TYPE-Ⅴ) ㎥ 1. 재료비

1) 폭약(D=50mm) : 0.31kg

2) 전기뇌관(각선길이, L=7.0m) : 0.04EA

3) 잡재료비(발파선, 전색재료 등) : 재료비의 5%

2. 노무비

1) 화약취급공 : 0.004인

2) 보통인부 : 0.006인

3. 기계경비

1) 유압식 크로울러드릴(110kW)

Q=0.014hr/㎥

소모자재(비트, 로드, 생크로드, 슬리브) : 기계경비의 24%

2) 굴삭기

Q=0.008hr/㎥

4. 집토(도쟈 32TON)

L=20m, f=1/1.625, E=0.35, q1=5.5, e=0.96

V1=40, V2=43, q0=q1×e=

cm=L/V1+L/V2+0.25=

Q=60×q0×f×E/cm= ㎥/hr

「건설표준품셈 공통부문

3-1-9 암발파(암발파

TYPE-Ⅴ)」 참조

- 846 -

번 호 공 종 단 위 단 가 기 준 비 고

h 대규모발파

(TYPE-Ⅵ)

㎥ 1. 재료비

1) 폭약(초유폭약, 기폭약포50mm, 에멀젼폭약1개) : 0.31kg

2) 전기뇌관(각선길이, L=13.0m) : 0.015EA

3) 잡재료비(발파선, 전색재료 등) : 재료비의 5%

2. 노무비

1) 화약취급공 : 0.002인

2) 보통인부 : 0.003인

3. 기계경비

1) 유압식 크로울러드릴(110kW)

Q=0.012hr/㎥

소모자재(비트, 로드, 생크로드, 슬리브) : 기계경비의 24%

2) 굴삭기

Q=0.004hr/㎥

4. 집토(도쟈 32TON)

L=20m, f=1/1.625, E=0.35, q1=5.5, e=0.96

V1=40, V2=43, q0=q1×e=

cm=L/V1+L/V2+0.25=

Q=60×q0×f×E/cm= ㎥/hr

「건설표준품셈 공통부문

3-1-10 암발파(대규모발파

TYPE-Ⅵ)」 참조

i 발파암 소할 ㎥ 1. 소 할 (유용량의 15%)

1)기계소할(굴삭기+대형브레이커)

Q=(9+11)/2=10㎥/hr

Q1=10×0.15=

2)치즐소모량

(0.006+0.02+0.03)/3=0.0186 본/hr

0.0186×0.15= 본/hr

「건설표준품셈 공통부문

8-2-15 대형브레이커」 참조

j 시험발파비 회 1. 2~3개 업체 견적 처리

- 847 -

번 호 공 종 단 위 단 가 기 준 비 고

1.06

a

a-1

유용토 운반

무대운반

토사

㎥

a-2 리핑암 ㎥

a-3 발파암 ㎥

b

b-1

도쟈운반

토사 ㎥

1. 도쟈운반 (32TON)

L= -20= m, f=1/1.3, q0=5.5, e=0.96(운반거리에 따른 기준 값 적용)

q=q0×e= ㎥

V1=52, V2=58, E=(0.7+0.6)/2=0.65

cm=L/V1+L/V2+0.25=

Q=60×q×f×E/cm= ㎥/hr

「건설표준품셈 공통부문

8-2-1 불도저」 참조

b-2 리핑암 ㎥ 1. 도쟈운반 (32TON)

L= -20= m, f=1/1.35, q0=5.5, e=0.96(운반거리에 따른 기준 값 적용)

q=q0×e= ㎥

V1=40, V2=58, E=(0.6+0.35)/2=0.48

cm=L/V1+L/V2+0.25=

Q=60×q×f×E/cm= ㎥/hr

「건설표준품셈 공통부문

8-2-1 불도저」 참조

b-3 발파암 ㎥ 1 도쟈운반 (32TON)

L= -20= m, f=1/1.625, q0=5.5, e=0.96(운반거리에 따른 기준 값 적용)

q=q0×e= ㎥

V1=40, V2=43, E=0.35

cm=L/V1+L/V2+0.25= 분

Q=60×q×f×E/cm= ㎥/hr

「건설표준품셈 공통부문

8-2-1 불도저」 참조

- 848 -

번 호 공 종 단 위 단 가 기 준 비 고

c

c-1

덤프운반

토사 ㎥ 1. 적 재 (로우더 2.87㎥ 타이어)

q0=2.87, K=1.2, f=1/1.3,

E0=(0.75+0.6)/2=0.68

m=1.8, L=8m, t1=9, t2=14

cm=(m×L)+t1+t2= sec

Q1=3600×q0×K×f×E0/cm= ㎥/hr

2. 운 반 (덤프 15TON)

L= km, E=0.9, f=1/1.3

q1=15/1.6ton/㎥×1.3=

n=q1/(2.87×K)= 회

T1=(cm×n)/(60×E0)= 분

T2=(L/15+L/20)×60= 분

T3=0.8, T4=0.42분, T5=0.5, T6=1.5

cm=T1+T2+T3+T4+T5+T6= 분

Q=60×q1×f×E/cm= ㎥/hr

「건설표준품셈 공통부문

8-2-5 로더 및 공통부문

8-2-8 덤프트럭」 참조

※ 현장 여건에 따라 적재하중

을 고려 24ton 장비를 비교 검

토하여 적용할 수 있음

※ 세륜기 통과 시에만 T6 적

용

c-2 리핑암 ㎥ 1. 적 재 (로우더 2.87㎥ 타이어)

q0=2.87, K=0.7, f=1/1.35,

E0=(0.6+0.55)/2=0.58

m=1.8, L=8m, t1=9, t2=14

cm=(m×L)+t1+t2= sec

Q1=3600×q0×K×f×E0/cm= ㎥/hr

2. 운 반 (덤프 15TON)

L= km, E=0.9, f=1/1.35

q1=15/1.9ton/㎥×1.35=

n=q1/(2.87×k)= 회

T1=(cm×n)/(60×E0)= 분

T2=(L/15+L/20)×60= 분

T3=0.8, T4=0.42분, T5=0.5, T6=1.5

cm=T1+T2+T3+T4+T5+T6= 분

Q=60×q1×f×E/cm= ㎥/hr

「건설표준품셈 공통부문

8-2-5 로더, 공통부문

8-2-8 덤프트럭」 참조

※ 세륜기 통과 시에만 T6 적

용

c-3 발파암 ㎥ 1 적 재 (굴삭기 1.0㎥)

q0=1.0, K=0.55, f=1/1.625, E0=0.45

cm=21 (135°)sec

Q1=3600×q0×K×f×E0/cm= ㎥/hr

2 운 반 (덤프 15TON)

L= km, f=1/1.625=, E=0.9,

q1=15/2.4×1.625=

n=q1/1.0×K= 회

T1=(cm×n)/(60×E0)= 분

T2=(L/15+L/20)×60= 분

T3=0.8, T4=0.42, T5=0.5, T6=1.5

cm=T1+T2+T3+T4+T5+T6= 분

Q=60×q1×f×E/cm= ㎥/hr

「건설표준품셈 공통부문

8-2-3 굴삭기, 공통부문

8-2-8 덤프트럭」 참조

※ 세륜기 통과 시에만 T6 적

용

- 849 -

번 호 공 종 단 위 단 가 기 준 비 고

1.07

a

순쌓기 운반

토 사 ㎥ ∙순쌓기량 : ㎥ ∙L= km

1. 벌개제근 : 별산

2. 깎기 (도쟈 32TON)

L= m, f=1/1.3, E=0.75

V1=40, V2=43, q0=5.5, e=0.96, q=q0×e=

cm=L/V1+L/V2+0.25= 분

Q1=60×q×f×E/cm= ㎥/hr

3. 적재 (로우더 2.87㎥)

q1=2.87, K=1.2, E0=(0.75+0.6)/2=0.68, f=1/1.3, m=1.8, l=8m

t1=9, t2=14

cm=(m×ℓ)+t1+t2=

Q2=3600×q1×K×f×E0/cm= ㎥/hr

4. 운반

1) 덤프 15TON : 80%

qt=15/1.6×1.3= , f=1/1.3, E1=0.9

n=qt/(2.87×K)= 회, T1=cm×n/(60×E0)= 분

T2=(L/15+L/20)×60= 분

T3=0.8, T4=0.42, T5=0.5, T6=1.5

cm=T1+T2+T3+T4+T5+T6= 분

Q=60×qt×f×E1/cm= ㎥/hr

2) 운반(덤프 24TON) : 20%

qt= 24/1.6×1.3= , f=1/1.3, E1=0.9

n=qt/(2.87×K)= 회, T1=cm×n/(60×E0)= 분

T2=(L/15+L/20)×60= 분

T3=0.8, T4=0.42, T5=0.5, T6=1.5

cm=T1+T2+T3+T4+T5+T6= 분

Q=60×qt×f×E1/cm= ㎥/hr

5. 원상복구비 : 별산

※순쌓기량이 100만㎥이상이고

운반거리가 10km이상인 공사

에 적용

「건설표준품셈 공통부문

8-2-1 불도저」 참조

「건설표준품셈 공통부문

8-2-5 로더」 참조

「건설표준품셈 공통부문

8-2-8 덤프트럭」 참조

※ 세륜기 통과 시에만 T6 적

용

※원상복구비는 별도로 복구

계획도에 의거 산출

- 850 -

번 호 공 종 단 위 단 가 기 준 비 고

b 리핑암 ㎥ ∙순쌓기량 : ㎥ ∙L= km

1. 벌개제근 : 별산

2. 깎 기

1) 리퍼도쟈 (리퍼2본 + 도쟈 32TON)

L=15m, An=0.4, f=1,

E0=(0.7+0.5+0.4)/3=0.53

cm=0.05×L+0.25= 분

Q=60×An×L×f×E0/cm= ㎥/hr

2) 집 토 (도쟈 32TON)

L1=20m, q0=5.5, e=0.96, f=1/1.35

E=(0.6+0.35)/2=0.48, V1=40, V2=43, q=q0×e=

cm=L/V1+L/V2+0.25=

Q=60×q×f×E/cm= ㎥/hr

3. 적재 (로우더 2.87㎥)

q1=2.87, K=0.7, E0=(0.6+0.55)/2=0.58, f=1/1.35, m=1.8, l=8m

t1= 9, t2=14

cm=(m×ℓ)+t1+t2=

Q2=3600×q1×K×f×E0/cm= ㎥/hr

4. 운반

1) 운반(덤프 15TON) : 80%

qt=15/1.9×1.35= , f=1/1.35, E1=0.9

n=qt/(2.87×K)= 회, T1=cm×n/(60×E0)= 분

T2=(L/15+L/20)×60= 분

T3=0.8, T4=0.42, T5=0.5, T6=1.5

cm=T1+T2+T3+T4+T5+T6= 분

Q=60×qt×f×E1/cm= ㎥/hr

※순쌓기량이 100만㎥이상이고

운반거리가 10km이상인 공사

에 적용

「건설표준품셈 공통부문

8-2-2 리퍼」 참조

「건설표준품셈 공통부문

8-2-1 불도저」 참조

「건설표준품셈 공통부문

8-2-5 로더」 참조

「건설표준품셈 공통부문

8-2-8 덤프트럭」 참조

※ 세륜기 통과 시에만 T6 적

용

- 851 -

번 호 공 종 단 위 단 가 기 준 비 고

2) 운반(덤프 24TON) : 20%

qt= 24/1.9×1.35= , f=1/1.35, E1=0.9

n=qt/(2.87×K)= 회, T1=cm×n/(60×E0)= 분

T2=(L/15+L/20)×60= 분

T3=0.8, T4=0.42, T5=0.5, T6=1.5

cm=T1+T2+T3+T4+T5+T6= 분

Q=60×qt×f×E1/cm= ㎥/hr

5. 원상복구비 : 별산

※ 세륜기 통과 시에만 T6 적

용

※원상복구비는 별도로 복구

계획도에 의거 산출

c 발파암 ㎥ ∙순쌓기량 : ㎥ ∙L= km

1. 벌개제근 : 별산

2. 재료비

1) 폭약(초유폭약, 기폭약포50mm, 에멀젼폭약1개) : 0.31kg

2) 전기뇌관(각선길이, L=13.0m) : 0.015EA

3) 잡재료비(발파선, 전색재료 등) : 재료비의 5%

3. 노무비

1) 화약취급공 : 0.002인

2) 보통인부 : 0.003인

4. 기계경비

1) 유압식 크로울러드릴(110kW)

Q=0.012hr/㎥

소모자재(비트, 로드, 생크로드, 슬리브) : 기계경비의 24%

2) 굴삭기(1.0㎥)

Q=0.004hr/㎥

※순쌓기량이 100만㎥이상이고

운반거리가 10km이상인 공사

에 적용

「건설표준품셈 공통부문

3-1-1 암발파(대규모발파

TYPE-Ⅳ)」 참조

- 852 -

번 호 공 종 단 위 단 가 기 준 비 고

5. 집토(도쟈 32TON)

L=20m, f=1/1.625, E=0.35, q1=5.5, e=0.96

V1=40, V2=43, q0=q1×e=

cm=L/V1+L/V2+0.25=

Q=60×q0×f×E/cm= ㎥/hr

6. 적재 ( 굴삭기(1.0㎥)

q1=1.0, K=0.55, , f=1/1.625, E0=0.45 ,Cm=21sec

Q=3600×q×K×f×E0/cm= ㎥/hr

7. 운반

1) 운반 (덤프 15TON) : 80%

qt=15/2.4×1.625= , f=1/1.625, E1=0.9

n=qt/(1.0×K)= 회, T1=cm×n/(60×E0)= 분

T2=(L/15+L/20)×60= 분

T3=0.8, T4=0.42, T5, T6=1.5

cm=T1+T2+T3+T4+T5+T6= 분

Q=60×qt×f×E1/cm= ㎥/hr

2) 운반(덤프 24TON) : 20%

qt=24/2.4×1.625= , f=1/1.625, E1=

n=qt/(1.0×K)= 회, T1=cm×n/(60×E0)= 분

T2=(L/15+L/20)×60= 분

T3=0.8, T4=0.42, T5=0.5, T6=1.5

cm=T1+T2+T3+T4+T5+T6= 분

Q=60×qt×f×E1/cm= ㎥/hr

8. 원상복구비 : 별산

「건설표준품셈 공통부문

8-2-1 불도저」 참조

「건설표준품셈 공통부문

8-2-3 굴삭기」 참조

「건설표준품셈 공통부문

8-2-8 덤프트럭」 참조

※ 세륜기 통과 시에만 T6 적

용

※원상복구비는 별도로 복구

계획도에 의거 산출

d 토취장 사용료 ㎥ 1. 토취장 사용료(토취장 면적의 순쌓기량의 해당 시,군 골재가의 1/2)

- ㎥×1/2=

- 853 -

번 호 공 종 단 위 단 가 기 준 비 고

1.08

a

사토

토사 ㎥ 1. 적 재 (로우더 2.87㎥ 타이어)

q1=2.87, K=1.2, E0=(0.75+0.6)/2=0.68, f=1/1.3,

m=1.8, L=8m, t1= 9, t2=14

cm1=(m×L)+t1+t2= sec

Q=3600×q1×K×f×E0/cm1= ㎥/hr

2. 운 반 (덤프 15TON)

L= km, f=1/1.3, E1=0.9

q2=15/1.6×1.3=

n=q2/(q1×K)= 회

T1=(cm1×n)/(60×E0)= 분

T2= 평균운반거리표 참조

T3=0.8, T4=0.42, T5=0.5, T6=1.5

cm=T1+T2+T3+T4+T5+T6= 분

Q=60×q2×f×E1/c㎡= ㎥/hr

3. 정 리 (도쟈 19TON) ※ 사토량의 1/3 적용

q3=3.2×0.96=

f=1/1.3, E=0.65

L=20, V1=75, V2=98

c㎥=L/V1+L/V2+0.25=

Q=60×q3×f×E/c㎥= ㎥/hr

4. 복구비 : 별도계상

「건설표준품셈 공통부문

8-2-5 로더」 참조

「건설표준품셈 공통부문

8-2-8 덤프트럭」 참조

※ 세륜기 통과 시에만 T6 적용

「건설표준품셈 공통부문

8-2-1 불도저」 참조

- 854 -

번 호 공 종 단 위 단 가 기 준 비 고

b 리핑암 ㎥ 1. 적 재 (로우더 2.87㎥, 타이어)

q1=2.87, K=0.7, E0=(0.6+0.55)/2=0.58, f=1/1.35

m=1.8, L=8m, t1= 9, t2=14

cm1=(m×L)+t1+t2= sec

Q1=3600×q1×K×f×E0/cm1= ㎥/hr

2. 운 반 (덤프 15TON)

L= km, f=1/1.35, E1=0.9

q2=15/1.9×1.35=

n=q2/(2.87×K)= 회

T1=(cm1×n)/(60×E0)= 분

T2= 평균운반거리표 참조

T3=0.8, T4=0.42, T5=0.5, T6=1.5

cm=T1+T2+T3+T4+T5+T6= 분, T0=c㎡-T1= 분

Q2=60×q2×f×E1/c㎡= ㎥/hr

3. 정 리 (도쟈 19TON) ※ 사토량의 1/3 적용

q3=3.2×0.96=

f=1/1.35, E=(0.6+0.35)/2=0.48

L=20, V1=75, V2=98

c㎥=L/V1+L/V2+0.25= 분

Q=60×q3×f×E/c㎥= ㎥/hr

4. 복구비 : 별도계상

「건설표준품셈 공통부문

8-2-5 로더」 참조

「건설표준품셈 공통부문

8-2-8 덤프트럭」 참조

※ 세륜기 통과 시에만 T6 적용

「건설표준품셈 공통부문

8-2-1 불도저」 참조

- 855 -

번 호 공 종 단 위 단 가 기 준 비 고

c 발파암 ㎥ 1. 적 재 ( 굴삭기 1.0㎥)

Q1=1.0, K=0.55, f=1/1.625, E0=0.45, cm1=21sec

Q1=3600×q1×k×f×E0/cm1= ㎥/hr

2. 운 반 (덤프 15TON)

L= km, f=1/1.625, E1=0.9

q2=15/2.4×1.625=

n=q2/(1.0×K)= 회

T1=(cm1×n)/(60×E0)= 분

T2=평균운반거리표 참조

T3=0.8, T4=0.42, T5=0.5, T6=1.5

cm=T1+T2+T3+T4+T5+T6= 분, T0=c㎡-T1= 분

Q2=60×q2×f×E1/c㎡= ㎥/hr

3. 정 리 (도쟈 19TON) ※ 사토량의 1/3 적용

q3=3.2×0.96=

f=1/1.625, E=0.35

L=20, V1=75, V2=98

c㎥=L/V1+L/V2+0.25= 분

Q=60×q3×f×E/c㎥= ㎥/hr

4. 복구비 : 별도계상

「건설표준품셈 공통부문

8-2-3 굴삭기」 참조

「건설표준품셈 공통부문

8-2-8 덤프트럭」 참조

※ 세륜기 통과 시에만 T6 적용

「건설표준품셈 공통부문

8-2-1 불도저」 참조

- 856 -

번 호 공 종 단 위 단 가 기 준 비 고

1.09

a

흙쌓기

노체 ㎥ 1. 포설 (모터그레이더 3.6m)

L=2.9m, H=0.3m, D1=50

E1=0.6, N1=4회, f=C/L

V1=6, V2=6.5, t=0.5

cm1=0.06×(D1/V1+D1/V2)+2×t= 분

Q1=60×L×D1×H×E×f/(N1×cm1)= m3/hr

2. 다짐

1) 진동로라 (자주식 10TON)

N2=6, V=4, W1=1.9, E2=0.6

D2=0.3, f=1

Q2=1000×V×W1×E2×D2×f/N2= m3/hr

2) 타이어로라 (8-15TON)

N3=4, V=2.5, W2=1.8, E3=0.6

D3=0.3, f=1

Q3=1000×V×W2×E3×D3×f/N3= m3/hr

3. 살수비 (물탱크 5500ℓ)

E4=0.9, L=1.0km, O.M.C=13%, N.M.C=8%

T1=5분(흡입준비), T3=10분(흡입시간)

T4=5분(살수대기), T5=20분(살수시간)

T2=1.0/15×2×60=8분(운반시간)

cm2=T1+T2+T3+T4+T5= 분

Q4=60×5500×0.9/cm2= 분

13%=Ww/Ws×100%

Ww=1600-Ws

13Ws=100-Ww

13Ws=(1600-Ws)×100

13Ws=160000-100Ws

113Ws=(1600-Ws)×100

Ws=(1600×100)/113=1415.92kg/m3

W(살수량)=Ws×(0.13-0.08)=70.80kg/m3

Q5=Q4/W= m3/hr

「건설표준품셈 공통부문

8-2-7 모터그레이더」 참조

「건설표준품셈 공통부문

8-2-9 롤러」 참조

「건설표준품셈 토목부분

6-9-5 하수관 준설(흡입식)」 참

조

- 857 -

번 호 공 종 단 위 단 가 기 준 비 고

b 노상 ㎥ 1. 포설 (모터그레이더 3.6m)

L=2.9m, H=0.2m, D1=50

E1=0.6, N1=4회, f=C/L

V1=6, V2=6.5, t=0.5

cm1=0.06×(D1/V1+D1/V2)+(2×t)= 분

Q1=60×L×D1×H×E×f/(N1×cm1)= m3/hr

2. 다짐

1) 진동로라 (자주식 10TON)

N2=6, V=4, W1=1.9, E2=0.6

D2=0.2, f=1

Q2=1000×V×W1×E2×D2×f/N2= m3/hr

2) 타이어로라 (8-15TON)

N3=4, V=2.5, W2=1.8, E3=0.6

D3=0.2, f=1

Q3=1000×V×W2×E3×D3×f/N3= m3/hr

3. 살수비 (물탱크 5500ℓ)

E4=0.9, L=1.0km, O.M.C=13%, N.M.C=8%

T1=5분(흡입준비), T3=10분(흡입시간)

T4=5분(살수대기), T5=20분(살수시간)

T2=1.0/15×2×60=8분(운반시간)

cm2=T1+T2+T3+T4+T5= 분

Q4=60×5500×0.9/cm2= 분

13%=Ww/Ws×100%

Ww=1600-Ws

13Ws=100-Ww

13Ws=(1600-Ws)×100

13Ws=160000-100Ws

113Ws=(1600-Ws)×100

Ws=(1600×100)/113=1415.92kg/m3

W(살수량)=Ws×(0.13-0.08)=70.80kg/m3

Q5=Q4/W= m3/hr

「건설표준품셈 공통부문

8-2-7 모터그레이더」 참조

「건설표준품셈 공통부문

8-2-9 롤러」 참조

「건설표준품셈 토목부분

6-9-5 하수관 준설(흡입식)」 참

조

- 858 -

번 호 공 종 단 위 단 가 기 준 비 고

c 녹지대 (비다짐) ㎥ 1. 적재 및 운반 (본선운반에 포함)

2. 녹지대 정지 (도쟈 32TON)

L=20m, f=1/1.3, q0=5.5, e=0.96

q=q0×e= , E=(0.7+0.6)/2=0.65

V1=70, V2=78

cm=L/V1+L/V2+0.25= 분

Q=60×q×f×E/cm= ㎥/hr

「건설표준품셈 공통부문

8-2-1 불도저」 참조

※ 녹지대 및 교차로, 램프 부근

조경 감안

d

d-1

암쌓기

암쌓기(다짐도 90%이상/㎥) ㎥ 1. 소할(15%) : 별도계상

2. 부설(발파암)

1) 불도저 (32TON)

L=20m, f=1/1.625, q0=5.5, e=0.96, E=0.35, q=q0×e= , V1=75, V2=98

cm=L/V1+L/V2+0.25= 분

Q=60×q×f×E/cm= ㎥/hr

3. 다짐

1) 인력품

특별인부 : 0.00059인

2) 양족식로울러 (32TON)

Q=0.0047hr/㎥

3) 진동롤러 (10TON)

Q=0.0047hr/㎥

4. 살수비 (물탱크 5500ℓ)

E4=0.9, L=1.0km, O.M.C=13%,

N.M.C=8%, T1=5분(흡입준비),

T3=10분(흡입시간),

T4=5분(살수대기),

T5=20분(살수시간),

T2=1.0/15×2×60 =8분(운반시간)

「건설표준품셈 공통부문

8-2-1 불도저」 참조

「건설표준품셈 공통부문

8-4-3 암성토」 참조

- 859 -

번 호 공 종 단 위 단 가 기 준 비 고

c㎡=T1+T2+T3+T4+T5= 분

Q4=60×5500×0.9/c㎡= 분

13%=Ww/Ws×100%

Ww=1600-Ws

13Ws=100-Ww

13Ws=(1600-Ws)×100

13Ws=160000-100Ws

113Ws=(1600-Ws)×100

Ws=(1600×100)/113=1415.92kg/㎥

W(살수량)=Ws×(0.13-0.08)

=70.80kg/㎥

Q5=Q4/W= ㎥/hr

d-2 필터층 ㎥ 1. 모래 구입 및 운반 : 별도계상

2. 포설

1) 모우터그레이다(3.6m)

W=2.9m, H=0.3m, D=50m

E=0.6, N=4회, f=C/L

V1=6.0, V2=6.5, t=0.5

cm=0.06×(D/V1+D/V2)+2×t= 분

Q=60×W×D×H×E×f/(N×cm)= ㎥/hr

3. 다짐

1) 진동로라 (자주식 10TON)

N=6, V=4, W1=1.9, E=0.6, H=0.3, f=1

Q=1000×V×W1×E×H×f/N= ㎥/hr

2) 타이어로라 (8-15TON)

N=4, V=2.5, W=1.8, E=0.6, H=0.3, f=1

Q=1000×V×W×E×H×f/N= ㎥/hr

「건설표준품셈 공통부문

8-2-7 모터그레이더」 참조

「건설표준품셈 공통부문

8-2-9 롤러」 참조

- 860 -

번 호 공 종 단 위 단 가 기 준 비 고

4. 살수비 (물탱크 5500ℓ)

E4=0.9, L=1.0km, O.M.C=13%,

N.M.C=8%, T1=5분(흡입준비),

T3=10분(흡입시간),

T4=5분(살수대기),

T5=20분(살수시간),

T2=1.0/15×2×60 =8분(운반시간)

c㎡=T1+T2+T3+T4+T5= 분

Q4=60×5500×0.9/c㎡= 분

13%=Ww/Ws×100%

Ww=1600-Ws

13Ws=100-Ww

13Ws=(1600-Ws)×100

13Ws=160000-100Ws

113Ws=(1600-Ws)×100

Ws=(1600×100)/113=1415.92kg/㎥

W(살수량)=Ws×(0.13-0.08)

=70.80kg/㎥

Q5=Q4/W= ㎥/hr

「건설표준품셈 토목부문

6-9-5 하수관 준설(흡입식)」 참

조

d-3 비탈면 흙쌓기 ㎥ 1. 포설 (굴삭기 0.7㎥)

q= 0.7, k=1.1, f=C/L, E=0.7, Cm=20sec

Q=3600×q×k×f×E/Cm= ㎥/hr

2. 다짐 (플레이트콤팩터 1.5TON)

V=1km/h, W=0.45m, E=0.6, N=3회, D=0.1m, f=1

Q=1,000×V×W×E×D×f/N=㎥/hr

「건설표준품셈 공통부문

8-2-3 굴삭기」 참조

「건설표준품셈 공통부문

8-2-10 플레이트 콤팩터」 참조

1.10 뒷채움 및 다짐공 ㎥ ※ 구조물공 4.04 참조

- 861 -

번 호 공 종 단 위 단 가 기 준 비 고

1.11

a

노상준비공

깎기부 ㎡

1. 긁어 일으키기

(도쟈 32TON+립퍼 3본)

H=0.2m, D1=50, E=0.85, f=1.0, Am=0.6,

Cm1=(0.05×D1)+0.25= 분

Q1=((60×Am×D1×E1)/(Cm1×H)= ㎡/hr

2. 노면정리 (그레이다 3.6m)

L=2.9m, D2=50m, E2=0.5, N1=2회, f=1.0

V1=6, V2=6.5, t=0.5분, H=0.2m

C㎡=0.06×(D2/V1+D2/V2)+(2×t)= 분

Q2=(60×L×D2×E2×H/(N1+C㎡×H))= ㎡/hr

3. 다짐

1) 진동로라 (자주식 10TON)

N2=6회, V0=4, W1=1.9, E3=0.6

f=1.0, D3=0.05m, H=0.2m

Q3=(1000×V0×W1×E3×f×D3/(N2×H))= ㎡/hr

2) 타이어로라 (자주식 8-15TON)

N3=1회, V=2.5, W2=1.8, E4=0.6

f=1.0, D4=0.05m, H=0.2m

Q4=(1000×V×W2×E4×f×D4/(N3×H))= ㎡/hr

「건설표준품셈 공통부문

8-2-1 불도저」 참조 「건설표준품셈 공통부문

8-2-2 리퍼」 참조

「건설표준품셈 공통부문

8-2-7 모터그레이더」 참조

「건설표준품셈 공통부문

8-2-9 롤러」 참조

- 862 -

번 호 공 종 단 위 단 가 기 준 비 고

b 기존도로부 ㎡ 1. 도로면 절취 및 정리 (그레이다 3.6m)

L=2.3, D1=50, E1=0.6, N1=2회, f=1.0

V1=6, V2=6.5, t=1.5분, H=0.05m

Cm1=0.06×(D1/V1+D1/V2)+2×t= 분

Q1=(60×L×D1×E1×H)/(N1×Cm1×H)= ㎡/hr

2. 다짐

1) 진동로라 (자주식 10TON)

N2=2회, V0=4, W1=1.9, E2=0.6

f=1.0, D2=0.05m, H=0.05m

Q2=(1000×V0×W1×E2×D2)/(N2×H)= ㎡/hr

2) 타이어로라 (8-15TON)

N3=1회, V=2.5, W2=1.8, E3=0.6

f=1.0, D2=0.05m, H=0.05m

Q3=(1000×V×W2×E3×f×D2)/(N3×H)= ㎡/hr

3. 살수비 (노상살수의 10%)

(물탱크 5500ℓ, L=1.0km) ∙소요살수량 5% : 1415.92kg/㎥×0.05=70.80kg/㎥

t1=5분 (준비), t3=10분 (흡입)

t4=5분 (대기), t5=20분 (살수)

V1=15km/hr, V2=15km/hr

C㎡=40+(1/15×60×2)= 분

Q4=(60×5.5×0.9/(C㎡×0.0708))×0.1= ㎡/hr

「건설표준품셈 공통부문

8-2-7 모터그레이더」 참조

「건설표준품셈 공통부문

8-2-9 롤러」 참조

「건설표준품셈 토목부문

6-9-5 하수관 준설(흡입식)」 참

조

1.12

a

되메우기 및 다짐

(기계 100%)

되메우기 및 다짐 ㎥ 1. 기계(100%) : 굴삭기 1.0㎥

q=1.0, k=0.9, f=0.9/1.3=0.692, E=0.65, cm=19sec(90˚)

Q=(3600×q×k×f×E)/cm=㎥/hr

2. 다짐(램머 80kg)

A=0.28×0.33=㎡, N= 36,000회/hr, H=0.15m,

f=1.0, E=0.5, P=57회

Q=(A×N×H×f×E)/P=㎥/hr

「건설표준품셈 공통부문

8-2-3 굴삭기」 참조 「건설표준품셈 공통부문

8-2-11 래머」 참조

※ 배수공의 L형측구, 부대공의 방

음벽 및 다이크 되메우기량 등에

적용

- 863 -

번 호 공 종 단 위 단 가 기 준 비 고

b 되메우기(비다짐)

㎥

1. 기계(100%) : 굴삭기 1.0㎥

q=1.0, k=0.9, f=1/L, E=0.65, cm= 19sec(90˚)

Q=(3600×q×k×f×E)/cm=㎥/hr

「건설표준품셈 공통부문

8-2-3 굴삭기」 참조

※ 배수공의 L형측구, 부대공의

방음벽 및 다이크 되메우기량 등

에 적용

1.13 쌓기비탈면다짐 ㎡ 1. 법면다짐(유압식 진동 콤펙터+굴삭기 0.7㎥)

A = 77.7 ㎡/hr

「건설표준품셈 공통부문

8-2-17 법면 다짐기」 참조

1.14 층따기 ㎥ 1. 법면 절취 (도쟈 19ton)

L=20m, f=1/1.3, E=0.60

V1=40, V2=46, q=3.2×0.96 =

Cm=L/V1+L/V2+0.25 =

Q=60×q×f×E/Cm = m3/hr

「건설표준품셈 공통부문

8-2-1 불도저」 참조

1.15

a

토공 규준틀설치

비탈규준틀 ea 1. 판재 (t=1.2cm, B=12cm, L=4m)

- 재료비 : (0.012×0.12×4)×0.5 =

2. 말뚝 (말구6cm, L=1.8m 2본)

A=(0.06×0.06)×3.14×1/4×1.8 =

- 재료비 : A×2본×0.5 =

3. 못 (75m/m)

- 재료비 : 0.03kg

4. 목공 : 0.16인

5. 보통인부 : 0.14인

「건설표준품셈 공통부문

2-5 규준틀」 참조

b 수평규준틀 ea 1. 목재 : 0.014m3×0.8 =

2. 못 (75m/m)

- 재료비 : 0.03kg

4. 목공 : 0.21인

5. 보통인부 : 0.19인

「건설표준품셈 공통부문

2-5 규준틀」 참조

- 864 -

번 호 공 종 단 위 단 가 기 준 비 고

1.16

a

연약지반 처리공

침하토 쌓기 및 다짐 ㎥ 1. 흙쌓기 노체다짐 참조

b 샌드매트 부설

(T= 0.5 m)

㎥ 1. 모래구입 : 별도계상

2. 모래운반 : 별도계상

3. 포설 (습지도쟈 13.0 Ton)

D =20m, E=0.70, e=0.96, f=0.9/1.15

V1=55m/분, V2=70m/분, t=0.25m

qo=1.5×e

cm=D/V1+D/V2)+0.25

Q1=60×qo×f×E/cm= m3/hr

4. 살수비 (물탱크 5500ℓ)

E4=0.9, L=1.0km, O.M.C=13%, N.M.C=8%

T1=5분(흡입준비), T3=10분(흡입시간)

T4=5분(살수대기), T5=20분(살수시간)

T2=1.0/15×2×60=8분(운반시간)

cm2=T1+T2+T3+T4+T5= 분

Q4=60×5500×0.9/cm2= 분

Ww=1600-Ws

13Ws=100-Ww

13Ws=(1600-Ws)×100

13Ws=160000-100Ws

113Ws=(1600-Ws)×100

Ws=(1600×100)/113=1415.92kg/m3

W(살수량)=Ws×(0.13-0.08)=70.80kg/m3

Q5=Q4/W= m3/hrWw=1950-Ws

5. 다짐

1) 진동로라 (자주식 10TON)

N2=6, V=4, W1=1.9, E2=0.6

D2=0.25, f=1.0

Q2=1000×V×W1×E2×D2×f/N2= m3/hr

「건설표준품셈 공통부문

8-2-1 불도저」 참조

「건설표준품셈 토목부문

6-9-5 하수관 준설(흡입식)」 참

조

「건설표준품셈 공통부문

8-2-9 롤러」 참조

- 865 -

번 호 공 종 단 위 단 가 기 준 비 고

c P.P매트 부설

(T= 5 Ton/m)

(T= 10 Ton/m)

(T= 15 Ton/m)

㎡ 1. 자재비

P.P매트 : 1.0㎡×1.10

2. 부설비

1) 보통인부 : 0.0007인

2) 특별인부 : 0.0014인

「건설표준품셈 공통부문

5-2-1 매트부설」 참조

d P.E.P매트 부설

(T= 15 Ton/m)

(T= 20 Ton/m)

㎡ 1. 자재비

P.E.P매트 : 1.0㎡×1.10

2. 부설비

1) 보통인부 : 0.0007인

2) 특별인부 : 0.0014인

「건설표준품셈 공통부문

5-2-1매트부설」 참조

e 샌드 드레인

(D 400mm)

m 총연장 : m , 총본수 : 본

평균연장 : 총연장/ 총본수 = m/본

※ 장비조합

- Casing 항타 및 인발

진동파일햄머+무한궤도 크레인+리더+모래말뚝 케이싱+발전기

- Casing내 모래투입 : 페이로더 1.34㎥/hr 타이어

공기압축기

※ 인력편성

보링공 : 1.0인

특별인부 : 1.0인

보통인부 : 1.0인

※ 작업소요시간

T=(T1+T2)/f

T1=2분, T2=L1×t1, t1=0.6분/m, f=0.8

「건설표준품셈 공통부문

5-2-4 모래말뚝」 참조

- 866 -

번 호 공 종 단 위 단 가 기 준 비 고

1. 모래구입 및 운반 : 별산

2. 중기사용료

1) 크레인(무한궤도)

L=20m 이하 50ton 1대

L=20~30m 80ton 1대

2) 진동파일해머

L=20m 이하 90kw 1대

L=20~30m 120kw 1대

3) 리더

L=20m 이하 31m 1대

L=20~30m 36m 1대

4) 모래말뚝 케이싱

L=20m 이하 22m 1대

L=20~30m 27m 1대

5) 공기압축기

L=20m 이하 10.3㎥ 1대

L=20~30m 17.0㎥ 1대

6) 발전기 350kw 1대

7) 로더 1.34㎥ 1대

3. 인건비

보링공 1인, 특별인부 1인, 보통인부 1인

4. 부속장비(스킵버킷, 공기탱크, 자동기록장치 등)의 기계경비 및 소요자재(용접봉, 호스

등) : 노무비의 9%

5. 장비조립 및 해체(회당)

소요일수 : 조립 2일, 해체 1일

기계설비공 1인, 특별인부 2인, 용접공 1인, 크레인 250ton 1대

- 867 -

번 호 공 종 단 위 단 가 기 준 비 고

f 샌드 콤팩션 파일

(D 700mm)

m 총연장 : m , 총본수 : 본

평균연장 : 총연장/ 총본수 = m/본

※ 장비조합

- Casing 항타 및 인발

진동파일햄머+무한궤도 크레인+리더+모래말뚝 케이싱+발전기

- Casing내 모래투입 : 페이로더 1.34㎥/hr 타이어

공기압축기

※ 인력편성

보링공 : 1.0인

특별인부 : 1.0인

보통인부 : 1.0인

※ 작업소요시간

T=(T1+T2)/f

T1=2분, T2=L1×t1, t1=0.6분/m, f=0.8

1. 모래구입 및 운반 : 별산

2. 중기사용료

1) 크레인(무한궤도)

L=20m 이하 50ton 1대

L=20~30m 80ton 1대

2) 진동파일해머

L=20m 이하 90kw 1대

L=20~30m 120kw 1대

3) 리더

L=20m 이하 31m 1대

L=20~30m 36m 1대

「건설표준품셈 공통부문

5-2-4 모래말뚝」 참조

- 868 -

번 호 공 종 단 위 단 가 기 준 비 고

4) 모래말뚝 케이싱

L=20m 이하 22m 1대

L=20~30m 27m 1대

5) 공기압축기

L=20m 이하 10.3㎥ 1대

L=20~30m 17.0㎥ 1대

6) 발전기 350kw 1대

7) 로더 1.34㎥ 1대

3. 인건비

보링공 1인, 특별인부 1인, 보통인부 1인

4. 부속장비(스킵버킷, 공기탱크, 자동기록장치 등)의 기계경비 및 소요자재(용접봉, 호스

등) : 노무비의 9%

5. 장비조립 및 해체(회당)

소요일수 : 조립 2일, 해체 1일

기계설비공 1인, 특별인부 2인, 용접공 1인, 크레인 250ton 1대

g 팩 드레인

(D 120mm)

m ※ Casing 제작

총연장: m , 총본수: 본

평균연장: 총연장/ 총본수= m/본

※ 장비조합

- Casing 항타 및 인발

무한궤도 크레인50Ton+진동파일햄머90KW+발전기350KW+리더31M+케이싱

22M+Skip Buckt10㎥+자동기록장치+Hopper1.0

- Casing내 모래투입

Air Compressor(17.0㎥/min 365CFM)+Air Hose(3/4")

- 작업조편성

작업반장:1.0인 비 계 공:1.0인 용 접 공:1.0인

특별인부:4.0인 보통인부:2.0인

- 869 -

번 호 공 종 단 위 단 가 기 준 비 고

※ Pack Drain 시공능력

Q=60*L*E/CM , L=타설길이(M) , E=(0.6+0.8)/2=0.70

T1=140 sec , T3=130 sec , T4=220 sec , T2=L/(0.08+0.05/2)= sec ,

T5=L/0.08= sec,

CM=T1+T2+T3+T4+T5= sec , Q1=(3600*L*0.7/CM)*4= M/HR

1. Casing 항타 및 인발

1) 크레인(무한궤도)50Ton

2) 진동파일햄머(90KW)

2. 재료비

1) Pack Drain:1.0m

2) 안내판:15.70 EA

3. 모래구입

4. 모래운반

5. Pack내 모래투입

1)페이로다(타이어)1.72㎥

Q1=1.72 , K=1.2 , F=0.78 , E=0.75

CM=1.8+8+6+14=29.80분, Q2=3600*Q1*K*F*E/CM=㎥/HR

(P.D 1본당 속채움모래량:외경 D=120m/m*4EA)

V=(3.14*(0.12**2)/4)*4=0.045㎥/m * 1.2(할증)=0.054㎥/m * L= ㎥/m

6. Air Compressor(10.3㎥/min 365CFM)

7. 발전기(350KW)

8. Air Hose(3/4")

9. 인력품

작업반장:1.0인, 비 계 공:1.0인, 용 접 공:1.0인,

특별인부:4.0인, 보통인부:2.0인

10. 자동기록장치 사용료:손료계상

11. Leader(31M):손료계상

- 870 -

번 호 공 종 단 위 단 가 기 준 비 고

12. Casing(22M):손료계상

13. Skip Bucket(10㎥):손료계상

14. Hopper(3.2㎥):손료계상

h 표토제거 ㎡ 1. 습지도쟈(13.0 Ton)

D=20.0m, E=0.4, e=0.96, f=1/1.3

V1=40m/분, V2=48m/분 , T=0.2 m

q0=1.5×e=

cm=D/V1+D/V2+0.25=

Q1=60×q0×f×E/cm= m3/hr

Q=Q1/T= m2/hr

「건설표준품셈 공통부문

8-2-1 불도저」 참조

i 과재쌓기 ㎥ 1. 포설 (모터그레이더 3.6m)

L=2.9m, H=0.3m, D1=50

E1=0.6, N1=4회, f=1.0

V1=6, V2=6.5, t=0.5

cm1=0.06×(D1/V1+D1/V2)+(2×t)= 분

Q1=60×L×D1×H×E×f/(N1×cm1)= m3/hr

「건설표준품셈 공통부문

8-2-7 모터그레이더」 참조

j 과재쌓기제거 ㎥ 1. 도 쟈(32.0 Ton)

D=20.0m, E=0.6, h=0.96, f=1/1.3

V1=40m/분, V2=43m/분 , T=0.2 m

q0=5.5×h=

cm=D/V1+D/V2+0.25=

Q1=60×q0×f×E/cm= ㎥/hr

2. 적 재 (로우더 2.87㎥ 타이어)

q0=2.87, K=1.2, f=1/1.3, E0=0.6

m=1.8, L=8m, t1=9, t2=14

cm=(m×L)+t1+t2= sec

Q1=3600×q0×K×f×E0/cm= ㎥/hr

3. 운 반 (덤프 15TON)

L= km, E=0.9, f=1/1.3

q1=15/1.6ton/m3×1.3=

n= q1 (2.87×k) = 회

T1=(cm×n)/(60×E0)= 분

T2=(L/15+L/20)×60= 분

T3=1.5, T4=0.7, T5=0.5, T6=1.5

cm=T1+T2+T3+T4+T5= 분

Q=60×q1×f×E/cm= m3/hr

「건설표준품셈 공통부문

8-2-1 불도저」 참조 「건설표준품셈 공통부문

8-2-5 로더」 참조 「건설표준품셈 공통부문

8-2-8 덤프트럭」 참조

※ 세륜기 통과 시에만 T6 적용

- 871 -

번 호 공 종 단 위 단 가 기 준 비 고

k 치환토 ㎥ 1. 습지도쟈(13 Ton)

D=20.0m, E=0.55, e=0.96, f=1/1.3

V1=40m/분, V2=48m/분

q0=1.5×e=

cm=D/V1+D/V2+0.25=

Q1=60×q0×f×E/cm= m3/hr

「건설표준품셈 공통부문

8-2-1 불도저」 참조

l 침하판 ea 1. 1인치 Pipe

1)철판(0.9*0.9*0.1) : 63.59 kg

2)강관(D=1") : 1.0m

3)고철

4)용접비(fillet용접 T=5m/m) : 0.107m(외경0.034*3.14)

2. 지지발이붙은 D=150m/m pipe

1)강관(D=150m/m) : 1.0m

2)원형봉강(D=16m/m , L=120cm 3EA) :

1.58kg*1.2m*3EA

3)Steel Plate(D=250 T=4m/m 3EA) :

1.54kg*3EA

4)고철

5)용접비(fillet용접 T=5m/m) : 0.9m

m 침하측정봉 및 보호관 m 1. 침하측정봉 및 보호관

1)1인치 Pipe : 1.0m

2)연결장치 : 재료비의 20%

2. 침하봉보호관(D=150m/m)

1)강관(D=150m/m) : 1.0m

2)연결장치 : 재료비의 20%

- 872 -

번 호 공 종 단 위 단 가 기 준 비 고

n 계측설치비 ea 1. 계측기

1) 기계손료: 개월

2. 재료비

평균심도(H)= m, 지 지 층(H1)= m, 상단여유고(H2)= m

D=H+H1+H2= m

1) ABS 수지 Casing(3m):4EA

2) ABS 수지 Casing Coupling:3EA

3) Rutter End Cap:2EA

4) 보호관:1EA

5) Sealing Type:1EA

3. 천공비

1) 소운반(리어카운반)

V=2000m/hr , T=5 min

N=(2000*450)/(120*200+2000*5)=26.47 회

Q=26.47*250/1000=6.62 ton

소요인수:N=3 ton/Q=0.45인

2) 기계기구설치

중급기술자:1.0인

초급기술자:1.0인

중급기능사:1.0인

3) 보링비(점토층)

천공길이:D1=H+H1= m

중급기술자:0.175인

보 링 공:0.350인

특수인부:0.350인

보통인부:0.350인

- 873 -

번 호 공 종 단 위 단 가 기 준 비 고

코아튜브:0.01EA

메탈크라운:0.025EA

드라이브파이프헤드:0.01EA

드라이브파이프슈:0.01EA

드라이브파이프:0.01EA

경유:2.132ℓ

잡유:0.2ℓ

4)기계기구손료:1.333hr

4. 계측 인력품

건설기술관리법시행령 제91조(품질시험 및 검사) 및 동법 시행규칙 제50조(품질시험 및 검

사의 실시)의 규정에 따라 건설업자는 품질시험 및 검사에 필요한 검사장비와 시험검사요원

을 건설공사의 공정에 따라 배치하여야 하고, 이에 소요되는 비용은 간접노무비에 포함되어

있으므로 계측을 위하여는 이에 필요한 측정용 기기설치에 따른 비용을 제외하고는 별도의

노무비를 계상하지 않는 것으로 한다.

5.계측분석비(조사)

∙분석인원

※ 간극수압계 분석비

- 특급기술자 A1=0.015인

- 고급기술자 B1=0.030인

- 중급기술자 C1=0.035인

※ 경사계 분석비

- 특급기술자 A2=0.020인

- 고급기술자 B2=0.040인

- 중급기술자 C2=0.050인

※ 변위말뚝 측정계 분석비

- 특급기술자 A3=0.010인

- 고급기술자 B3=0.020인

- 중급기술자 C3=0.025인

- 874 -

번 호 공 종 단 위 단 가 기 준 비 고

※ 지표침하판 분석비

- 특급기술자 A4=0.005인

- 고급기술자 B4=0.010인

- 중급기술자 C4=0.010인

1.17 자재운반비

a 모래 운반 m3 1. 구 입 : 별도계상

2. 운 반(덤프 15ton 80% + 덤프 24ton 20% )

Q= 60×qt×f×E/Cm

1.18

a

사급 자재대

모 래(상차도) m3 재료비 : 시중 물가지 참고

번호 제목 글쓴이 날짜 조회 수
공지 국토교통부_기준_자료목록 입니다 황대장 2021.05.18 174795
공지 국토교통부_방침_자료목록 입니다 황대장 2021.05.18 181929
공지 국토교통부_지침_자료목록 입니다 황대장 2021.05.18 176956
1233 2025_국도건설공사설계실무요령_제02편공종별수량내역서및산출요령_01-09_공종별수량내역서_부대공 file 효선 2026.10.12 102
1232 2025_국도건설공사설계실무요령_제02편공종별수량내역서및산출요령_02-01_수량산출요령_토공 file 효선 2026.10.12 122
1231 2025_국도건설공사설계실무요령_제02편공종별수량내역서및산출요령_02-02_수량산출요령_비탈면공 file 효선 2026.10.12 105
1230 2025_국도건설공사설계실무요령_제02편공종별수량내역서및산출요령_02-03_수량산출요령_배수공 file 효선 2026.10.12 127
1229 2025_국도건설공사설계실무요령_제02편공종별수량내역서및산출요령_02-04_수량산출요령_구조물공 file 효선 2026.10.12 136
1228 2025_국도건설공사설계실무요령_제02편공종별수량내역서및산출요령_02-05_수량산출요령_지하차도공 file 효선 2026.10.12 139
1227 2025_국도건설공사설계실무요령_제02편공종별수량내역서및산출요령_02-06_수량산출요령_터널공 file 효선 2026.10.12 125
1226 2025_국도건설공사설계실무요령_제02편공종별수량내역서및산출요령_02-07_수량산출요령_포장공 file 효선 2026.10.12 142
1225 2025_국도건설공사설계실무요령_제02편공종별수량내역서및산출요령_02-08_수량산출요령_교통안전시설공 file 효선 2026.10.12 138
1224 2025_국도건설공사설계실무요령_제02편공종별수량내역서및산출요령_02-09_수량산출요령_부대시설공 file 효선 2026.10.12 122
» 2025_국도건설공사설계실무요령_제02편공종별수량내역서및산출요령_03-01_단가산출요령_토공 file 효선 2026.10.12 142
1222 2025_국도건설공사설계실무요령_제02편공종별수량내역서및산출요령_03-02_단가산출요령_비탈면공 file 효선 2026.10.12 138
1221 2025_국도건설공사설계실무요령_제02편공종별수량내역서및산출요령_03-03_단가산출요령_배수공 file 효선 2026.10.12 280
1220 2025_국도건설공사설계실무요령_제02편공종별수량내역서및산출요령_03-04_단가산출요령_구조물공 file 효선 2026.10.12 140
1219 2025_국도건설공사설계실무요령_제02편공종별수량내역서및산출요령_03-05_단가산출요령_지하차도공 file 효선 2026.10.12 144
1218 2025_국도건설공사설계실무요령_제02편공종별수량내역서및산출요령_03-06_단가산출요령_터널공 file 효선 2026.10.12 171
1217 2025_국도건설공사설계실무요령_제02편공종별수량내역서및산출요령_03-08_단가산출요령_교통안전시설공 file 효선 2026.10.12 146
1216 2025_국도건설공사설계실무요령_제02편공종별수량내역서및산출요령_03-08_단가산출요령_교통안전시설공 file 효선 2026.10.12 206
1215 2025_국도건설공사설계실무요령_제02편공종별수량내역서및산출요령_03-09_단가산출요령_부대시설공 file 효선 2026.10.12 135
1214 2025_국도건설공사설계실무요령_제03편공종별표준도_01_토공 file 효선 2026.10.12 200