기준 2025_국도건설공사설계실무요령_제02편공종별수량내역서및산출요령_03-01_단가산출요령_토공
2026.10.12 14:06
/ 제 3 장 /
단가산출요령
1. 토공 ···································································································· 829
2. 비탈면공 ····························································································· 875
3. 배수공 ································································································ 891
4. 구조물공 ····························································································· 955
5. 지하차도공 ························································································· 992
6. 터널공 ································································································ 998
7. 포장공 ······························································································ 1019
8. 교통안전시설공 ················································································ 1040
9. 부대공 ······························································································ 1060
- 829 -
1 토공
번 호 공 종 단 위 단 가 기 준 비 고
1.01
a
a-1
기존구조물 깨기
무근콘크리트 깨기
무근콘크리트
(T=30cm 미만)
㎥ 1. 깨 기
1) 기 계 (100%)
① 대형브레이커+굴삭기 (0.7㎥)
Q=(3.3+5.9)/2=4.6㎥/m
② 작업보조원
- 보통인부 1인
③ 치즐소모량 (0.7㎥용)
- 0.01본/hr
2. 집토 (굴삭기 1.0㎥)
q= 1.0, k=0.55, f=1/1.50, E=0.35, Cm=21sec
Q=3600×q×k×f×E/Cm= ㎥/hr
※ 적사 및 운반은 건설폐기물 파쇄, 또는 폐기물 상차및 운반비에서 적용
「건설표준품셈 공통부문
8-2-15 대형브레이커」 참조
「건설표준품셈 공통부문
8-2-3 굴삭기」 참조
a-2 무근콘크리트
(T=30cm 이상)
㎥ 1. 깨 기
1) 기 계 (100%)
① 대형브레이커+굴삭기 (0.7㎥)
Q=(2.6+4.6)/2=3.60㎥/hr
② 작업보조원
- 보통인부 1인
③ 치즐소모량 (0.7㎥용)
- 0.01본/hr
2. 집토 (굴삭기 1.0㎥)
q= 1.0, k=0.55, f=1/1.50, E=0.35, Cm=21sec
Q=3600×q×k×f×E/Cm= ㎥/hr
※ 적사및 운반은 건설폐기물 파쇄, 또는 폐기물 상차및 운반비에서 적용
「건설표준품셈 공통부문
8-2-15 대형브레이커」 참조
「건설표준품셈 공통부문
8-2-3 굴삭기」 참조
- 830 -
번 호 공 종 단 위 단 가 기 준 비 고
b
b-1
철근콘크리트 깨기
철근 콘크리트
(T=30cm 미만)
㎥ 1. 깨 기
1) 기 계 (100%)
① 대형브레이커+굴삭기 (0.7m3)
Q=(1.6+3.3)/2=2.45m3/m
② 작업보조원
- 보통인부 1인
③ 치즐소모량 (0.7m3용)
- 0.01본/hr
2. 철근절단
- 용 접 공 : 0.02인
- 보통인부 : 0.08인
- 아세칠렌 : 0.05kg
- 산 소 : 135L
3. 집토 (굴삭기 1.0m3)
q= 1.0, k=0.55, f=1/1.50, E=0.35, Cm=21sec
Q=3600×q×k×f×E/Cm= m3/hr
※ 적사및 운반은 건설폐기물 파쇄, 또는 폐기물 상차및 운반비에서 적용
4. 고철공제
A=1㎥ ×0.008×7,850kkg/㎥ ×80%=50.24 kg/m3 ≒ 50 kg/m3
「건설표준품셈 공통부문
8-2-15 대형브레이커」 참조
단가기준에 나와있는 스타일로
일괄 변경
이후 메모 변경
「건설표준품셈 건축부문
제12장 유지보수공사
12-3-2 콘크리트 구조물헐기」
참조
「건설표준품셈 공통부문
8-2-3 굴삭기」 참조
- 831 -
번 호 공 종 단 위 단 가 기 준 비 고
b-2 철근 콘크리트
(T=30cm 이상)
㎥ 1. 깨 기
1) 기 계
① 대형브레이커+굴삭기 (0.7m3)
Q=(1.4+2.7)/2=2.05m3/m
② 작업보조원
- 보통인부 1인
③ 치즐소모량(0.7m3용)
- 0.01본/hr
2. 철근절단
- 용 접 공 : 0.02인
- 보통인부 : 0.08인
- 아세칠렌 : 0.05kg
- 산 소 : 135L
3. 집토 (굴삭기 1.0m3)
q= 1.0, k=0.55, f=1/1.50, E=0.35, Cm=21sec
Q=3600×q×k×f×E/Cm= m3/hr
※ 적사및 운반은 건설폐기물 파쇄, 또는 폐기물 상차및 운반비에서 적용
4. 고철공제
A=1㎥ ×0.008×7,850kkg/㎥ ×80%=50.24 kg/m3 ≒ 50 kg/m3
「건설표준품셈 공통부문
8-2-15 대형브레이커」참조
「건설표준품셈 건축부문
제12장 유지보수공사
12-3-2 콘크리트 구조물헐기」
참조
「건설표준품셈 공통부문
8-2-3 굴삭기」 참조
c
c-1
석축헐기
석축헐기(찰쌓기) ㎡ 1. 인력철거
- 보통인부 : 0.6인
2. 잡재료비 (인력품의 5%)
3. 소 운 반 (리어카 L=20m)
Rt=(132+264+340)/3=245.33kg/m2
L=20m, V=2500, t1=5, T=450시간
N=V×T/(120×L+V×t1)= 회/인
Q=(N×250)/Rt= m2/인
- 보통인부 : 2인
「건설표준품셈 건축부문
12-3-4 석축 벽돌 헐기 및 콘
크리트 부수기」 참조
※ 유용할 경우만 적용
- 832 -
번 호 공 종 단 위 단 가 기 준 비 고
c-2 석축헐기(메쌓기) ㎡ 1. 인력철거
- 보통인부 (뒷길이 60cm 이내) : 0.2인
- 보통인부 (뒷길이 60cm 이상) : 0.3인
2. 잡재료비 (인력품의 5%)
3. 소 운 반 (리어카 L=20m)
Rt=(132+264+340)/3=245.33kg/㎡
L=20m, V=2500, t1=5, T=450시간
N=V×T/(120×L+V×t1)= 회/인
Q=(N×250)/Rt= ㎡/인
- 보통인부 : 2인
「건설표준품셈 건축부문
12-3-4 석축 벽돌 헐기 및 콘
크리트 부수기」 참조
※ 유용할 경우만 적용
d
d-1
기존포장 깨기
콘크리트 (기계) ㎥ 1. 기계 깨기
1) 깨기 (대형브레이커+굴삭기 (0.7㎥))
Q=(3.3+5.9)/2=4.6㎥/hr
2) 치즐소모량 (0.7㎥용)
0.01본/hr
3) 작업보조원
- 보통인부 : 1인
2. 집토 (굴삭기 1.0㎥)
q= 1.0, k=0.55, f=1/1.50, E=0.35, Cm=21sec
Q=3600×q×k×f×E/Cm= ㎥/hr
※ 적사및 운반은 건설폐기물 파쇄, 또는 폐기물 상차및 운반비에서 적용
「건설표준품셈 공통부문
8-2-15 대형브레이커」 참조
「건설표준품셈 공통부문
8-2-3 굴삭기」 참조
d-2 아스팔트 (기계) ㎥ 1. 기계 깨기
1) 깨기 (대형브레이커+ 굴삭기 (0.7㎥))
Q=16.5㎥/hr(아스콘 포장 30cm 미만), 12.5㎥/hr(아스콘 포장 30cm 이상)
2) 치즐소모량 (0.7㎥용)
0.01본/hr
3) 작업보조원
- 보통인부 : 1인
「건설표준품셈 공통부문
8-2-15 대형브레이커 헐기」
참조
- 833 -
번 호 공 종 단 위 단 가 기 준 비 고
2. 집토 (굴삭기 1.0㎥)
q= 1.0, k=0.55, f=1/1.50, E=0.35, Cm=21sec
Q=3600×q×k×f×E/Cm= ㎥/hr
※ 적사및 운반은 건설폐기물 파쇄, 또는 폐기물 상차및 운반비에서 적용
「건설표준품셈 공통부문
8-2-3 굴삭기」 참조
d-3 보도블럭 포장헐기 ㎡ 1. 인력철거
-설치품의 50%
1) 시공량 : 소형고압블록 A=300㎡/일, 대형블록 A=270㎡/일, 보도용콘크리트블록
A=370㎡/일
2) 특별인부 2인/일
보통인부 4인/일
3) 플레이트콤팩터(1.5ton) 1대/일
굴삭기(0.6㎥) 1대/일
4) 잡재료비(인력품의 5%)
5) 공구손료(인력품의 3%)
2.소운반(리어카) L=20m
t1=5, V=2500, T=450, L=20m
N=V×T/(120×L+V×t1)= 회/인
Q=N×250kg/2300kg/㎥÷T(두께) = ㎡/인
- 보통인부 : 2인
「건설표준품셈 토목부문
1-11-20 보도용 블록 포장 철
거」 참조
e
e-1
포장절단
콘크리트(기계) m 1. 운전경비
1) 블레이드 (D=320~400mm, T=3.2mm 기준) 0.0031개
2) 보통인부 1인/일
특별인부 1인/일
3) 물운반
L=0.1km, V=2.5km/hr
N=(2500×450)/(120×100+2500×4)= 회/일
Q=N×250/1000= ℓ/일
- 보통인부 : 2인
「건설표준품셈 토목부문
1-7-1 콘크리트포장 절단」
참조
- 834 -
번 호 공 종 단 위 단 가 기 준 비 고
2. 기계사용료
1) 콘크리트 컷트 (320~40mm)
Q=60m/일
2) 동력분무기 (4.85kw) 0.5대/일
e-2 아스팔트(기계) m 1. 운전경비
1) 블레이드 (D=320~400mm, T=3.2mm 기준) 0.0027개
2) 보통인부 1인/일
특별인부 1인/일
3) 물운반
L=0.1km, V=2.5km/hr
N=(2500×450)/(120×100+2500×4)= 회/일
Q=N×250/1000= ℓ/일
- 보통인부 : 2인
2. 기계사용료
1) 콘크리트 컷트 (320~40mm)
Q=60m/일
2) 동력분무기 (4.85kw) 0.5대/일
「건설표준품셈 토목부문
1-7-2 아스콘포장 절단」
참조
f 호안블록 헐기 ㎡ ※ 가설비의 50% 적용
1. 크레인 10Ton : 0.048hr
2. 인력품
특별인부 : 0.017인, 보통인부 : 0.007인
「건설표준품셈 토목부문
2-3-3 블록 붙이기(기계)」
참조
g 돌망태 헐기 ㎡ ※ 가설비의 50% 적용
제1장 굴삭기 1.0㎥ : 0.030hr
제2장 인력품
석공 : 0.044인, 특별인부 : 0.014인, 보통인부 : 0.006인
「건설표준품셈 토목부문
2-2-1 타원형 돌망태 설치」
참조
h 가드레일 철거 m ※ 교통안전시설공 8.04 가드레일 설치비의 50% 적용
가드레일 일반구간, 단부, 중앙분리대구간으로 구분
「건설표준품셈 토목부문
1-11-21 가드레일 철거」
참조
i 강교철거 ton ※ 가설비의 50% 적용
1. 크레인 100Ton(무한궤도) : 2대
2. 인력품
특별인부 : 8인, 보통인부 : 6인
3. 콘크리트깨기 : 별도계상
- 835 -
번 호 공 종 단 위 단 가 기 준 비 고
j P.S.C Beam 철거 본
k 건설폐기물 파쇄 ㎥ 1. 콘크리트 및 아스콘깨기 : 별도계상
2. 적 재 : 타이어 페이로더 2.87m3
q0=2.87, K=0.55, f=1/1.50, E0=0.35
m=1.8, L=8m, t1=9, t2=14
cm=(m×L)+t1+t2= sec
Q1=3600×q0×K×f×E0/cm= m3/hr
3. 운 반 (덤프 15TON+자동덮개)
L=공사연장/4, E=0.9, f=1/1.50
q1=15/2.3 ×1.50 =
n=q1/(2.87×K)= 회
T1=(cm×n)/(60×E0)= 분
T2=(L/15+L/20)×60= 분
T3=0.8, T4=0.42분, T5=0.5, T6=1.5
cm=T1+T2+T3+T4+T5+T6= 분
Q=60×q1×f×E/cm= m3/hr
4. 크라샤투입 : 타이어페이로더 2.87m3
q = 2.87 , f=1.0 , K=0.55 , E=0.35 , T1=9, T2=14
Cm=1.8×20+T1+T2 = sec
Q=3600×q×K×f×E/Cm = m3/hr
3. 크라싱(이동식크라샤150TON)
Qc= 273 ton/hr , E=0.40
Qp2=Qc×E = ton/hr
Q = Qp2/2.3ton/hr = m3/hr
「건설표준품셈 공통부문
8-2-5 로더」 참조
「건설표준품셈 공통부문
8-2-8 덤프트럭」 참조
「건설표준품셈 공통부문
8-2-14 크러셔」 참조
1.02 측구 뚝쌓기
(인력)
㎥ 1. 인력품
보통인부 : 0.11인
「건설표준품셈 공통부문
3-2-1 인력 흙 다지기」 참조
- 836 -
번 호 공 종 단 위 단 가 기 준 비 고
1.03
a
표토제거
답구간 ㎡ 1. 도 쟈 (19TON)
T=0.2m, D=20m E=0.55, e=0.96, f=1/1.3
V1=40m/분, V2=46m/분
q0=3.2×e=
cm=D/V1+D/V2+0.25=
Q1=60×q0×f×E/cm= m3/hr
Q=Q1/T= m2/hr
「건설표준품셈 공통부문
8-2-1 불도저」 참조
* 표토제거
T=0.2m
b 답외구간 ㎡ 1. 도 쟈 (32TON)
T=0.2m, D=20m, E=0.65, e=0.96, f=1/1.3
V1=40m/분, V2=43m/분
q0=5.5×e=
cm=D/V1+D/V2+0.25=
Q1=60×q0×f×E/cm= m3/hr
Q=Q1/T= m2/hr
「건설표준품셈 공통부문
8-2-1불도저」 참조
* 표토제거
T=0.2m
c 비옥토 수거 1. 도 쟈 (32TON)
T=0.2m, D=20m, E=0.65, e=0.96, f=1/1.3
V1=40m/분, V2=43m/분
q0=5.5×e=
cm=D/V1+D/V2+0.25=
Q1=60×q0×f×E/cm= ㎥/hr
Q=Q1/T= ㎡/hr
「건설표준품셈 공통부문
8-2-1 불도저」 참조
* 비옥토 수거
T=0.2m
1.04
a
a-1
벌개제근 및 가로수 제거
벌개제근(벌목비포함)
뿌리뽑기 ㎡
∘ 입목본수도 : 50~60% ∘ 수 경 : 10~20cm ∘ 수 종 : (침엽+잡목+활엽)/3 ∘ 집재거리는 100m기준, 이를 초과하는 경우 100m 증가마다 인력품 30%씩 가산
1. 노무비
1) 보통인부 : 0.00106인
2. 집재(굴삭기+부착용집게 0.2㎥)
Q=0.00376hr/㎥
「건설표준품셈 공통부문
3-7-2 뿌리뽑기」 참조
- 837 -
번 호 공 종 단 위 단 가 기 준 비 고
a-2 벌목 ㎡ ∘ 나무높이 : 5m이상~8m미만 ∘ 집재거리는 100m기준, 이를 초과하는 경우 100m 증가마다 인력품 30%씩 가산
1. 노무비
1) 벌 목 부 : 0.00280인
2) 보통인부 : 0.00066인
2. 공구손료 및 경장비(인력품의 10%)
3. 집재(굴삭기+부착용집게 0.2㎥)
Q=0.00354hr/㎥
「건설표준품셈 공통부문
3-7-1벌목」 참조
b 가로수 제거 본 1. 가로수 제거 (굴삭기 0.7㎥)
소요시간 15분/본 (평균이동거리 10m 포함)
Q=60/15= 본/hr
2. 보통인부 : 1인×15분/450= 인
3. 운 반 (덤프트럭 15TON)
q=4.9×2.2×0.94= ㎥/대
k=0.9, N=q/0.7= 본/대, L=2km
t1=2.96×14= 분, t2=(L/15+L/20)×60= 분
t3=0.8, t4=0.42
cm=t1+t2+t3+t4=
Q1=60×q×k/cm= ㎥/hr
Q2=Q1/0.7= 본/hr
4. 뿌리제거(폐기물 처리비) : 부대공 일괄적용
「건설표준품셈 공통부문
8-2-3 굴삭기」 참조
「건설표준품셈 공통부문
8-2-8 덤프트럭」 참조
1.05
a a-1
흙깎기
토사
토사(도쟈 19TON) ㎥ 1. 깎 기
1) 도쟈 (19TON) : 공사규모가 적고, 흙의 성질이 약한 것
L=20m, f=1/1.30, E=0.60, V1=40, V2=46
q0=3.2, e=0.96, q=q0×e=
cm=L/V1+L/V2+0.25= 분
Q=60×q×f×E/cm= ㎥/hr
「건설표준품셈 공통부문
8-2-1 불도저」 참조
a-2 토사(도쟈 32TON) ㎥ 1) 도쟈 (32TON) : 공사규모가 크고, 흙의 성질이 단단한 것
L=20m, f=1/1.30, E=0.60, V1=40, V2=43
q0=5.5, e=0.96, q=q0×e=
cm=L/V1+L/V2+0.25=
Q=60×q×f×E/cm= ㎥/hr
「건설표준품셈 공통부문
8-2-1 불도저」 참조
- 838 -
번 호 공 종 단 위 단 가 기 준 비 고
b 리핑암 ㎥ 1. 깎 기
1) 리퍼도쟈 (리퍼2본 + 도쟈 32TON)
L=15m, An=0.4, f=1,
E0=(0.7+0.5+0.4)/3=0.53
cm=0.05×L+0.25= 분
Q=60×An×L×f×E0/cm= ㎥/hr
2) 집 토 (도쟈 32TON)
L=20m, q0=5.5, e=0.96, f=1/1.35 (1.3~1.35)
E=0.48, V1=40, V2=43, q=q0×e=
cm=L/V1+L/V2+0.25=
Q=60×q×f×E/cm= ㎥/hr
「건설표준품셈 공통부문
8-2-2 리퍼」 참조
「건설표준품셈 공통부문
8-2-1 불도저」 참조
c
c-1
발파암 깎기
브레이커(기계) ㎥ 브레이커 90% +발파 10%
1. 암석 절취(10%)
1) 암석절취
① 폭약 : 0.35kg
② 뇌관 : 1.0EA
③ 비트 : 0.008EA
④ 화약취급공 : 0.041인
⑤ 보통인부 : 0.103인
⑥ 착암공 : 0.041인
2) 기계사용료 : 편절암 참조
① 소형브레이커(2.7㎥/min) : 0.203 hr
② 공기압축기(10.3㎥/min) : 0.074 hr
2. 깎 기(90%)
1) 대형브레이커 + 굴삭기 (0.7㎥) ∙(연암+보통암+경암)/3×0.9=
2) 치즐소모량 (0.7㎥) : 0.018본/hr×0.9
3. 집 토 (도쟈 32TON)
L=20m, f=1/1.625, E=0.25, q1=5.5, H=0.96
V1=40, V2=43, q0=q1×H=
cm=L/V1+L/V2+0.25=
Q=60×q0×f×E/cm= ㎥/hr
「건설표준품셈 공통부문
3-1-11 암발파(소형브레이커)」
참조
「건설표준품셈 공통부문
8-2-15 대형브레이커」 참조
「건설표준품셈 공통부문
8-2-1 불도저」 참조
- 839 -
번 호 공 종 단 위 단 가 기 준 비 고
c-2 소형브레이커 ㎥ 1. 재료비
1) 폭약 : 0.35kg
2) 뇌관 : 1.0EA
3) 비트 : 0.008EA
2. 노무비
1) 화약취급공 : 0.0041인
2) 착 암 공 : 0.041인
3) 보통인부 : 0.103인
3. 기계경비
1) 소형브레이커(2.7㎥/min)
Q=0.203hr/㎥
2) 에어호스(1.91cm)
Q=0.203hr/㎥
3) 공기압축기(10.3㎥/min)
Q=0.074hr/㎥
4. 집토(도쟈 32TON)
L=20m, f=1/1.625, E=0.25, q1=5.5, e=0.96
V1=40, V2=43, q0=q1×e=
cm=L/V1+L/V2+0.25=
Q=60×q0×f×E/cm= ㎥/hr
「건설표준품셈 공통부문
3-1-11 암발파(소형브레이커)」
참조
「건설표준품셈 공통부문
8-2-15 대형브레이커」 참조
「건설표준품셈 공통부문
8-2-1 불도저」 참조
- 840 -
번 호 공 종 단 위 단 가 기 준 비 고
d
d-1
미진동 굴착공법
미진동굴착
(TYPE-1)
m3 1. 재료비
1) 미진동파쇄제 : 0.313kg
2) 잡재료비 (주재료비의 5%)
2. 노무비
1) 화약취급공 : 0.040인
2) 보통인부 : 0.060인
3. 기계경비
1) 유압식 크로울러드릴(110kW)
Q=0.100hr/㎥
소모자재(비트, 로드, 생크로드, 슬리브) : 기계경비의 24%
2) 굴삭기(1.0㎥)+대형브레이커(2차 파쇄)
Q=0.040hr/㎥
소모자재(치즐) : 기계경비의 5%
4. 발파 보호공
1) 보통인부 : 0.125인/회
2) 굴삭기(1.0㎥) : 1.0hr/회
3) 보호매트의 재료비는 별도 계상
5. 집토(도쟈 32TON)
L=20m, f=1/1.625, E=0.35, q1=5.5, e=0.96
V1=40, V2=43, q0=q1×e=
cm=L/V1+L/V2+0.25=
Q=60×q0×f×E/cm= ㎥/hr
「건설표준품셈 공통부문
3-1-5 암발파(미진동굴착
TYPE-Ⅰ)」 참조
- 841 -
번 호 공 종 단 위 단 가 기 준 비 고
d-2 유압식 할암공법 ㎥ 1. 재료비
1) 유압할암봉 : 0.022개
2. 노무비
1) 기계설비공 : 0.068인
2) 특별인부 : 0.271인
3. 기계경비
1) 유압식 크로울러드릴(110kW)
Q=0.121hr/㎥
소모자재(비트, 로드, 생크로드, 슬리브) : 기계경비의 24%
2) 발전기(25kW)
Q=0.486hr/㎥
3) 유압식 할암기(Ø80mm)
Q=0.486hr/㎥
4) 굴삭기+대형브레이커(2차 파쇄)
Q=0.121hr/㎥
소모자재(치즐) : 기계경비의 2%
4. 발파 보호공
1) 보통인부 : 0.125인/회
2) 굴삭기(1.0㎥) : 1.0hr/회
3) 보호매트의 재료비는 별도 계상한다.
5. 집토(도쟈 32TON)
L=20m, f=1/1.625, E=0.35, q1=5.5, e=0.96
V1=40, V2=43, q0=q1×e=
cm=L/V1+L/V2+0.25=
Q=60×q0×f×E/cm= ㎥/hr
「건설표준품셈 공통부문
3-1-4 암파쇄(유압식 할암공법
」 참조
- 842 -
번 호 공 종 단 위 단 가 기 준 비 고
e 정밀진동제어발파
(TYPE-Ⅱ)
㎥ 1. 재료비
1) 폭약(D=25mm) : 0.25kg
2) 전기뇌관(L=3.5m) : 0.99EA
3) 잡재료비(발파선, 전색재료 등) : 재료비의 5%
2. 노무비
1) 화약취급공 : 0.023인
2) 보통인부 : 0.032인
3. 기계경비
1) 유압식 크로울러드릴(110kW)
Q=0.080hr/㎥
소모자재(비트, 로드, 생크로드, 슬리브) : 기계경비의 24%
2) 굴삭기+대형브레이커(2차 파쇄)
Q=0.025hr/㎥
소모자재(치즐) : 기계경비의 5%
4. 발파 보호공
1) 보통인부 : 0.125인/회
2) 굴삭기(1.0㎥) : 1.0hr/회
3) 보호매트의 재료비는 별도 계상한다.
5. 집토(도쟈 32TON)
L=20m, f=1/1.625, E=0.35, q1=5.5, e=0.96
V1=40, V2=43, q0=q1×e=
cm=L/V1+L/V2+0.25=
Q=60×q0×f×E/cm= ㎥/hr
「건설표준품셈 공통부문
3-1-6 암발파(정밀진동제어발
파 TYPE-Ⅱ)」 참조
- 843 -
번 호 공 종 단 위 단 가 기 준 비 고
f f-1
진동제어발파
진동제어(소규모)발파
(TYPE-Ⅲ)
㎥ 1. 재료비
1) 폭약(D=32mm) : 0.35kg
2) 전기뇌관(L=3.5m) : 0.35EA
3) 잡재료비(발파선, 전색재료 등) : 재료비의 5%
2. 노무비
1) 화약취급공 : 0.012인
2) 보통인부 : 0.017인
3. 기계경비
1) 유압식 크로울러드릴(110kW)
Q=0.049hr/㎥
소모자재(비트, 로드, 생크로드, 슬리브) : 기계경비의 24%
2) 굴삭기
Q=0.013hr/㎥
4. 발파 보호공
1) 보통인부 : 0.125인/회
2) 굴삭기(1.0㎥) : 1.0hr/회
3) 보호매트의 재료비는 별도 계상한다.
5. 집토(도쟈 32TON)
L=20m, f=1/1.625, E=0.35, q1=5.5, e=0.96
V1=40, V2=43, q0=q1×e=
cm=L/V1+L/V2+0.25=
Q=60×q0×f×E/cm= ㎥/hr
「건설표준품셈 공통부문
3-1-7 암발파(소규모진동제어
발파 TYPE-Ⅲ)」 참조
- 844 -
번 호 공 종 단 위 단 가 기 준 비 고
f-2 진동제어(중규모)발파
(TYPE-Ⅳ)
㎥ 1. 재료비
1) 폭약(D=32mm) : 0.33kg
2) 전기뇌관(각선길이, L=4.5m) : 0.11EA
3) 잡재료비(발파선, 전색재료 등) : 재료비의 5%
2. 노무비
1) 화약취급공 : 0.007인
2) 보통인부 : 0.009인
3. 기계경비
1) 유압식 크로울러드릴(110kW)
Q=0.021hr/㎥
소모자재(비트, 로드, 생크로드, 슬리브) : 기계경비의 24%
2) 굴삭기
Q=0.009hr/㎥
4. 발파 보호공
1) 보통인부 : 0.125인/회
2) 굴삭기(1.0㎥) : 1.0hr/회
3) 보호매트의 재료비는 별도 계상한다.
「건설표준품셈 공통부문
3-1-8 암발파(중규모진동제어
발파 TYPE-Ⅳ)」 참조
- 845 -
번 호 공 종 단 위 단 가 기 준 비 고
g 일반발파
(TYPE-Ⅴ) ㎥ 1. 재료비
1) 폭약(D=50mm) : 0.31kg
2) 전기뇌관(각선길이, L=7.0m) : 0.04EA
3) 잡재료비(발파선, 전색재료 등) : 재료비의 5%
2. 노무비
1) 화약취급공 : 0.004인
2) 보통인부 : 0.006인
3. 기계경비
1) 유압식 크로울러드릴(110kW)
Q=0.014hr/㎥
소모자재(비트, 로드, 생크로드, 슬리브) : 기계경비의 24%
2) 굴삭기
Q=0.008hr/㎥
4. 집토(도쟈 32TON)
L=20m, f=1/1.625, E=0.35, q1=5.5, e=0.96
V1=40, V2=43, q0=q1×e=
cm=L/V1+L/V2+0.25=
Q=60×q0×f×E/cm= ㎥/hr
「건설표준품셈 공통부문
3-1-9 암발파(암발파
TYPE-Ⅴ)」 참조
- 846 -
번 호 공 종 단 위 단 가 기 준 비 고
h 대규모발파
(TYPE-Ⅵ)
㎥ 1. 재료비
1) 폭약(초유폭약, 기폭약포50mm, 에멀젼폭약1개) : 0.31kg
2) 전기뇌관(각선길이, L=13.0m) : 0.015EA
3) 잡재료비(발파선, 전색재료 등) : 재료비의 5%
2. 노무비
1) 화약취급공 : 0.002인
2) 보통인부 : 0.003인
3. 기계경비
1) 유압식 크로울러드릴(110kW)
Q=0.012hr/㎥
소모자재(비트, 로드, 생크로드, 슬리브) : 기계경비의 24%
2) 굴삭기
Q=0.004hr/㎥
4. 집토(도쟈 32TON)
L=20m, f=1/1.625, E=0.35, q1=5.5, e=0.96
V1=40, V2=43, q0=q1×e=
cm=L/V1+L/V2+0.25=
Q=60×q0×f×E/cm= ㎥/hr
「건설표준품셈 공통부문
3-1-10 암발파(대규모발파
TYPE-Ⅵ)」 참조
i 발파암 소할 ㎥ 1. 소 할 (유용량의 15%)
1)기계소할(굴삭기+대형브레이커)
Q=(9+11)/2=10㎥/hr
Q1=10×0.15=
2)치즐소모량
(0.006+0.02+0.03)/3=0.0186 본/hr
0.0186×0.15= 본/hr
「건설표준품셈 공통부문
8-2-15 대형브레이커」 참조
j 시험발파비 회 1. 2~3개 업체 견적 처리
- 847 -
번 호 공 종 단 위 단 가 기 준 비 고
1.06
a
a-1
유용토 운반
무대운반
토사
㎥
a-2 리핑암 ㎥
a-3 발파암 ㎥
b
b-1
도쟈운반
토사 ㎥
1. 도쟈운반 (32TON)
L= -20= m, f=1/1.3, q0=5.5, e=0.96(운반거리에 따른 기준 값 적용)
q=q0×e= ㎥
V1=52, V2=58, E=(0.7+0.6)/2=0.65
cm=L/V1+L/V2+0.25=
Q=60×q×f×E/cm= ㎥/hr
「건설표준품셈 공통부문
8-2-1 불도저」 참조
b-2 리핑암 ㎥ 1. 도쟈운반 (32TON)
L= -20= m, f=1/1.35, q0=5.5, e=0.96(운반거리에 따른 기준 값 적용)
q=q0×e= ㎥
V1=40, V2=58, E=(0.6+0.35)/2=0.48
cm=L/V1+L/V2+0.25=
Q=60×q×f×E/cm= ㎥/hr
「건설표준품셈 공통부문
8-2-1 불도저」 참조
b-3 발파암 ㎥ 1 도쟈운반 (32TON)
L= -20= m, f=1/1.625, q0=5.5, e=0.96(운반거리에 따른 기준 값 적용)
q=q0×e= ㎥
V1=40, V2=43, E=0.35
cm=L/V1+L/V2+0.25= 분
Q=60×q×f×E/cm= ㎥/hr
「건설표준품셈 공통부문
8-2-1 불도저」 참조
- 848 -
번 호 공 종 단 위 단 가 기 준 비 고
c
c-1
덤프운반
토사 ㎥ 1. 적 재 (로우더 2.87㎥ 타이어)
q0=2.87, K=1.2, f=1/1.3,
E0=(0.75+0.6)/2=0.68
m=1.8, L=8m, t1=9, t2=14
cm=(m×L)+t1+t2= sec
Q1=3600×q0×K×f×E0/cm= ㎥/hr
2. 운 반 (덤프 15TON)
L= km, E=0.9, f=1/1.3
q1=15/1.6ton/㎥×1.3=
n=q1/(2.87×K)= 회
T1=(cm×n)/(60×E0)= 분
T2=(L/15+L/20)×60= 분
T3=0.8, T4=0.42분, T5=0.5, T6=1.5
cm=T1+T2+T3+T4+T5+T6= 분
Q=60×q1×f×E/cm= ㎥/hr
「건설표준품셈 공통부문
8-2-5 로더 및 공통부문
8-2-8 덤프트럭」 참조
※ 현장 여건에 따라 적재하중
을 고려 24ton 장비를 비교 검
토하여 적용할 수 있음
※ 세륜기 통과 시에만 T6 적
용
c-2 리핑암 ㎥ 1. 적 재 (로우더 2.87㎥ 타이어)
q0=2.87, K=0.7, f=1/1.35,
E0=(0.6+0.55)/2=0.58
m=1.8, L=8m, t1=9, t2=14
cm=(m×L)+t1+t2= sec
Q1=3600×q0×K×f×E0/cm= ㎥/hr
2. 운 반 (덤프 15TON)
L= km, E=0.9, f=1/1.35
q1=15/1.9ton/㎥×1.35=
n=q1/(2.87×k)= 회
T1=(cm×n)/(60×E0)= 분
T2=(L/15+L/20)×60= 분
T3=0.8, T4=0.42분, T5=0.5, T6=1.5
cm=T1+T2+T3+T4+T5+T6= 분
Q=60×q1×f×E/cm= ㎥/hr
「건설표준품셈 공통부문
8-2-5 로더, 공통부문
8-2-8 덤프트럭」 참조
※ 세륜기 통과 시에만 T6 적
용
c-3 발파암 ㎥ 1 적 재 (굴삭기 1.0㎥)
q0=1.0, K=0.55, f=1/1.625, E0=0.45
cm=21 (135°)sec
Q1=3600×q0×K×f×E0/cm= ㎥/hr
2 운 반 (덤프 15TON)
L= km, f=1/1.625=, E=0.9,
q1=15/2.4×1.625=
n=q1/1.0×K= 회
T1=(cm×n)/(60×E0)= 분
T2=(L/15+L/20)×60= 분
T3=0.8, T4=0.42, T5=0.5, T6=1.5
cm=T1+T2+T3+T4+T5+T6= 분
Q=60×q1×f×E/cm= ㎥/hr
「건설표준품셈 공통부문
8-2-3 굴삭기, 공통부문
8-2-8 덤프트럭」 참조
※ 세륜기 통과 시에만 T6 적
용
- 849 -
번 호 공 종 단 위 단 가 기 준 비 고
1.07
a
순쌓기 운반
토 사 ㎥ ∙순쌓기량 : ㎥ ∙L= km
1. 벌개제근 : 별산
2. 깎기 (도쟈 32TON)
L= m, f=1/1.3, E=0.75
V1=40, V2=43, q0=5.5, e=0.96, q=q0×e=
cm=L/V1+L/V2+0.25= 분
Q1=60×q×f×E/cm= ㎥/hr
3. 적재 (로우더 2.87㎥)
q1=2.87, K=1.2, E0=(0.75+0.6)/2=0.68, f=1/1.3, m=1.8, l=8m
t1=9, t2=14
cm=(m×ℓ)+t1+t2=
Q2=3600×q1×K×f×E0/cm= ㎥/hr
4. 운반
1) 덤프 15TON : 80%
qt=15/1.6×1.3= , f=1/1.3, E1=0.9
n=qt/(2.87×K)= 회, T1=cm×n/(60×E0)= 분
T2=(L/15+L/20)×60= 분
T3=0.8, T4=0.42, T5=0.5, T6=1.5
cm=T1+T2+T3+T4+T5+T6= 분
Q=60×qt×f×E1/cm= ㎥/hr
2) 운반(덤프 24TON) : 20%
qt= 24/1.6×1.3= , f=1/1.3, E1=0.9
n=qt/(2.87×K)= 회, T1=cm×n/(60×E0)= 분
T2=(L/15+L/20)×60= 분
T3=0.8, T4=0.42, T5=0.5, T6=1.5
cm=T1+T2+T3+T4+T5+T6= 분
Q=60×qt×f×E1/cm= ㎥/hr
5. 원상복구비 : 별산
※순쌓기량이 100만㎥이상이고
운반거리가 10km이상인 공사
에 적용
「건설표준품셈 공통부문
8-2-1 불도저」 참조
「건설표준품셈 공통부문
8-2-5 로더」 참조
「건설표준품셈 공통부문
8-2-8 덤프트럭」 참조
※ 세륜기 통과 시에만 T6 적
용
※원상복구비는 별도로 복구
계획도에 의거 산출
- 850 -
번 호 공 종 단 위 단 가 기 준 비 고
b 리핑암 ㎥ ∙순쌓기량 : ㎥ ∙L= km
1. 벌개제근 : 별산
2. 깎 기
1) 리퍼도쟈 (리퍼2본 + 도쟈 32TON)
L=15m, An=0.4, f=1,
E0=(0.7+0.5+0.4)/3=0.53
cm=0.05×L+0.25= 분
Q=60×An×L×f×E0/cm= ㎥/hr
2) 집 토 (도쟈 32TON)
L1=20m, q0=5.5, e=0.96, f=1/1.35
E=(0.6+0.35)/2=0.48, V1=40, V2=43, q=q0×e=
cm=L/V1+L/V2+0.25=
Q=60×q×f×E/cm= ㎥/hr
3. 적재 (로우더 2.87㎥)
q1=2.87, K=0.7, E0=(0.6+0.55)/2=0.58, f=1/1.35, m=1.8, l=8m
t1= 9, t2=14
cm=(m×ℓ)+t1+t2=
Q2=3600×q1×K×f×E0/cm= ㎥/hr
4. 운반
1) 운반(덤프 15TON) : 80%
qt=15/1.9×1.35= , f=1/1.35, E1=0.9
n=qt/(2.87×K)= 회, T1=cm×n/(60×E0)= 분
T2=(L/15+L/20)×60= 분
T3=0.8, T4=0.42, T5=0.5, T6=1.5
cm=T1+T2+T3+T4+T5+T6= 분
Q=60×qt×f×E1/cm= ㎥/hr
※순쌓기량이 100만㎥이상이고
운반거리가 10km이상인 공사
에 적용
「건설표준품셈 공통부문
8-2-2 리퍼」 참조
「건설표준품셈 공통부문
8-2-1 불도저」 참조
「건설표준품셈 공통부문
8-2-5 로더」 참조
「건설표준품셈 공통부문
8-2-8 덤프트럭」 참조
※ 세륜기 통과 시에만 T6 적
용
- 851 -
번 호 공 종 단 위 단 가 기 준 비 고
2) 운반(덤프 24TON) : 20%
qt= 24/1.9×1.35= , f=1/1.35, E1=0.9
n=qt/(2.87×K)= 회, T1=cm×n/(60×E0)= 분
T2=(L/15+L/20)×60= 분
T3=0.8, T4=0.42, T5=0.5, T6=1.5
cm=T1+T2+T3+T4+T5+T6= 분
Q=60×qt×f×E1/cm= ㎥/hr
5. 원상복구비 : 별산
※ 세륜기 통과 시에만 T6 적
용
※원상복구비는 별도로 복구
계획도에 의거 산출
c 발파암 ㎥ ∙순쌓기량 : ㎥ ∙L= km
1. 벌개제근 : 별산
2. 재료비
1) 폭약(초유폭약, 기폭약포50mm, 에멀젼폭약1개) : 0.31kg
2) 전기뇌관(각선길이, L=13.0m) : 0.015EA
3) 잡재료비(발파선, 전색재료 등) : 재료비의 5%
3. 노무비
1) 화약취급공 : 0.002인
2) 보통인부 : 0.003인
4. 기계경비
1) 유압식 크로울러드릴(110kW)
Q=0.012hr/㎥
소모자재(비트, 로드, 생크로드, 슬리브) : 기계경비의 24%
2) 굴삭기(1.0㎥)
Q=0.004hr/㎥
※순쌓기량이 100만㎥이상이고
운반거리가 10km이상인 공사
에 적용
「건설표준품셈 공통부문
3-1-1 암발파(대규모발파
TYPE-Ⅳ)」 참조
- 852 -
번 호 공 종 단 위 단 가 기 준 비 고
5. 집토(도쟈 32TON)
L=20m, f=1/1.625, E=0.35, q1=5.5, e=0.96
V1=40, V2=43, q0=q1×e=
cm=L/V1+L/V2+0.25=
Q=60×q0×f×E/cm= ㎥/hr
6. 적재 ( 굴삭기(1.0㎥)
q1=1.0, K=0.55, , f=1/1.625, E0=0.45 ,Cm=21sec
Q=3600×q×K×f×E0/cm= ㎥/hr
7. 운반
1) 운반 (덤프 15TON) : 80%
qt=15/2.4×1.625= , f=1/1.625, E1=0.9
n=qt/(1.0×K)= 회, T1=cm×n/(60×E0)= 분
T2=(L/15+L/20)×60= 분
T3=0.8, T4=0.42, T5, T6=1.5
cm=T1+T2+T3+T4+T5+T6= 분
Q=60×qt×f×E1/cm= ㎥/hr
2) 운반(덤프 24TON) : 20%
qt=24/2.4×1.625= , f=1/1.625, E1=
n=qt/(1.0×K)= 회, T1=cm×n/(60×E0)= 분
T2=(L/15+L/20)×60= 분
T3=0.8, T4=0.42, T5=0.5, T6=1.5
cm=T1+T2+T3+T4+T5+T6= 분
Q=60×qt×f×E1/cm= ㎥/hr
8. 원상복구비 : 별산
「건설표준품셈 공통부문
8-2-1 불도저」 참조
「건설표준품셈 공통부문
8-2-3 굴삭기」 참조
「건설표준품셈 공통부문
8-2-8 덤프트럭」 참조
※ 세륜기 통과 시에만 T6 적
용
※원상복구비는 별도로 복구
계획도에 의거 산출
d 토취장 사용료 ㎥ 1. 토취장 사용료(토취장 면적의 순쌓기량의 해당 시,군 골재가의 1/2)
- ㎥×1/2=
- 853 -
번 호 공 종 단 위 단 가 기 준 비 고
1.08
a
사토
토사 ㎥ 1. 적 재 (로우더 2.87㎥ 타이어)
q1=2.87, K=1.2, E0=(0.75+0.6)/2=0.68, f=1/1.3,
m=1.8, L=8m, t1= 9, t2=14
cm1=(m×L)+t1+t2= sec
Q=3600×q1×K×f×E0/cm1= ㎥/hr
2. 운 반 (덤프 15TON)
L= km, f=1/1.3, E1=0.9
q2=15/1.6×1.3=
n=q2/(q1×K)= 회
T1=(cm1×n)/(60×E0)= 분
T2= 평균운반거리표 참조
T3=0.8, T4=0.42, T5=0.5, T6=1.5
cm=T1+T2+T3+T4+T5+T6= 분
Q=60×q2×f×E1/c㎡= ㎥/hr
3. 정 리 (도쟈 19TON) ※ 사토량의 1/3 적용
q3=3.2×0.96=
f=1/1.3, E=0.65
L=20, V1=75, V2=98
c㎥=L/V1+L/V2+0.25=
Q=60×q3×f×E/c㎥= ㎥/hr
4. 복구비 : 별도계상
「건설표준품셈 공통부문
8-2-5 로더」 참조
「건설표준품셈 공통부문
8-2-8 덤프트럭」 참조
※ 세륜기 통과 시에만 T6 적용
「건설표준품셈 공통부문
8-2-1 불도저」 참조
- 854 -
번 호 공 종 단 위 단 가 기 준 비 고
b 리핑암 ㎥ 1. 적 재 (로우더 2.87㎥, 타이어)
q1=2.87, K=0.7, E0=(0.6+0.55)/2=0.58, f=1/1.35
m=1.8, L=8m, t1= 9, t2=14
cm1=(m×L)+t1+t2= sec
Q1=3600×q1×K×f×E0/cm1= ㎥/hr
2. 운 반 (덤프 15TON)
L= km, f=1/1.35, E1=0.9
q2=15/1.9×1.35=
n=q2/(2.87×K)= 회
T1=(cm1×n)/(60×E0)= 분
T2= 평균운반거리표 참조
T3=0.8, T4=0.42, T5=0.5, T6=1.5
cm=T1+T2+T3+T4+T5+T6= 분, T0=c㎡-T1= 분
Q2=60×q2×f×E1/c㎡= ㎥/hr
3. 정 리 (도쟈 19TON) ※ 사토량의 1/3 적용
q3=3.2×0.96=
f=1/1.35, E=(0.6+0.35)/2=0.48
L=20, V1=75, V2=98
c㎥=L/V1+L/V2+0.25= 분
Q=60×q3×f×E/c㎥= ㎥/hr
4. 복구비 : 별도계상
「건설표준품셈 공통부문
8-2-5 로더」 참조
「건설표준품셈 공통부문
8-2-8 덤프트럭」 참조
※ 세륜기 통과 시에만 T6 적용
「건설표준품셈 공통부문
8-2-1 불도저」 참조
- 855 -
번 호 공 종 단 위 단 가 기 준 비 고
c 발파암 ㎥ 1. 적 재 ( 굴삭기 1.0㎥)
Q1=1.0, K=0.55, f=1/1.625, E0=0.45, cm1=21sec
Q1=3600×q1×k×f×E0/cm1= ㎥/hr
2. 운 반 (덤프 15TON)
L= km, f=1/1.625, E1=0.9
q2=15/2.4×1.625=
n=q2/(1.0×K)= 회
T1=(cm1×n)/(60×E0)= 분
T2=평균운반거리표 참조
T3=0.8, T4=0.42, T5=0.5, T6=1.5
cm=T1+T2+T3+T4+T5+T6= 분, T0=c㎡-T1= 분
Q2=60×q2×f×E1/c㎡= ㎥/hr
3. 정 리 (도쟈 19TON) ※ 사토량의 1/3 적용
q3=3.2×0.96=
f=1/1.625, E=0.35
L=20, V1=75, V2=98
c㎥=L/V1+L/V2+0.25= 분
Q=60×q3×f×E/c㎥= ㎥/hr
4. 복구비 : 별도계상
「건설표준품셈 공통부문
8-2-3 굴삭기」 참조
「건설표준품셈 공통부문
8-2-8 덤프트럭」 참조
※ 세륜기 통과 시에만 T6 적용
「건설표준품셈 공통부문
8-2-1 불도저」 참조
- 856 -
번 호 공 종 단 위 단 가 기 준 비 고
1.09
a
흙쌓기
노체 ㎥ 1. 포설 (모터그레이더 3.6m)
L=2.9m, H=0.3m, D1=50
E1=0.6, N1=4회, f=C/L
V1=6, V2=6.5, t=0.5
cm1=0.06×(D1/V1+D1/V2)+2×t= 분
Q1=60×L×D1×H×E×f/(N1×cm1)= m3/hr
2. 다짐
1) 진동로라 (자주식 10TON)
N2=6, V=4, W1=1.9, E2=0.6
D2=0.3, f=1
Q2=1000×V×W1×E2×D2×f/N2= m3/hr
2) 타이어로라 (8-15TON)
N3=4, V=2.5, W2=1.8, E3=0.6
D3=0.3, f=1
Q3=1000×V×W2×E3×D3×f/N3= m3/hr
3. 살수비 (물탱크 5500ℓ)
E4=0.9, L=1.0km, O.M.C=13%, N.M.C=8%
T1=5분(흡입준비), T3=10분(흡입시간)
T4=5분(살수대기), T5=20분(살수시간)
T2=1.0/15×2×60=8분(운반시간)
cm2=T1+T2+T3+T4+T5= 분
Q4=60×5500×0.9/cm2= 분
13%=Ww/Ws×100%
Ww=1600-Ws
13Ws=100-Ww
13Ws=(1600-Ws)×100
13Ws=160000-100Ws
113Ws=(1600-Ws)×100
Ws=(1600×100)/113=1415.92kg/m3
W(살수량)=Ws×(0.13-0.08)=70.80kg/m3
Q5=Q4/W= m3/hr
「건설표준품셈 공통부문
8-2-7 모터그레이더」 참조
「건설표준품셈 공통부문
8-2-9 롤러」 참조
「건설표준품셈 토목부분
6-9-5 하수관 준설(흡입식)」 참
조
- 857 -
번 호 공 종 단 위 단 가 기 준 비 고
b 노상 ㎥ 1. 포설 (모터그레이더 3.6m)
L=2.9m, H=0.2m, D1=50
E1=0.6, N1=4회, f=C/L
V1=6, V2=6.5, t=0.5
cm1=0.06×(D1/V1+D1/V2)+(2×t)= 분
Q1=60×L×D1×H×E×f/(N1×cm1)= m3/hr
2. 다짐
1) 진동로라 (자주식 10TON)
N2=6, V=4, W1=1.9, E2=0.6
D2=0.2, f=1
Q2=1000×V×W1×E2×D2×f/N2= m3/hr
2) 타이어로라 (8-15TON)
N3=4, V=2.5, W2=1.8, E3=0.6
D3=0.2, f=1
Q3=1000×V×W2×E3×D3×f/N3= m3/hr
3. 살수비 (물탱크 5500ℓ)
E4=0.9, L=1.0km, O.M.C=13%, N.M.C=8%
T1=5분(흡입준비), T3=10분(흡입시간)
T4=5분(살수대기), T5=20분(살수시간)
T2=1.0/15×2×60=8분(운반시간)
cm2=T1+T2+T3+T4+T5= 분
Q4=60×5500×0.9/cm2= 분
13%=Ww/Ws×100%
Ww=1600-Ws
13Ws=100-Ww
13Ws=(1600-Ws)×100
13Ws=160000-100Ws
113Ws=(1600-Ws)×100
Ws=(1600×100)/113=1415.92kg/m3
W(살수량)=Ws×(0.13-0.08)=70.80kg/m3
Q5=Q4/W= m3/hr
「건설표준품셈 공통부문
8-2-7 모터그레이더」 참조
「건설표준품셈 공통부문
8-2-9 롤러」 참조
「건설표준품셈 토목부분
6-9-5 하수관 준설(흡입식)」 참
조
- 858 -
번 호 공 종 단 위 단 가 기 준 비 고
c 녹지대 (비다짐) ㎥ 1. 적재 및 운반 (본선운반에 포함)
2. 녹지대 정지 (도쟈 32TON)
L=20m, f=1/1.3, q0=5.5, e=0.96
q=q0×e= , E=(0.7+0.6)/2=0.65
V1=70, V2=78
cm=L/V1+L/V2+0.25= 분
Q=60×q×f×E/cm= ㎥/hr
「건설표준품셈 공통부문
8-2-1 불도저」 참조
※ 녹지대 및 교차로, 램프 부근
조경 감안
d
d-1
암쌓기
암쌓기(다짐도 90%이상/㎥) ㎥ 1. 소할(15%) : 별도계상
2. 부설(발파암)
1) 불도저 (32TON)
L=20m, f=1/1.625, q0=5.5, e=0.96, E=0.35, q=q0×e= , V1=75, V2=98
cm=L/V1+L/V2+0.25= 분
Q=60×q×f×E/cm= ㎥/hr
3. 다짐
1) 인력품
특별인부 : 0.00059인
2) 양족식로울러 (32TON)
Q=0.0047hr/㎥
3) 진동롤러 (10TON)
Q=0.0047hr/㎥
4. 살수비 (물탱크 5500ℓ)
E4=0.9, L=1.0km, O.M.C=13%,
N.M.C=8%, T1=5분(흡입준비),
T3=10분(흡입시간),
T4=5분(살수대기),
T5=20분(살수시간),
T2=1.0/15×2×60 =8분(운반시간)
「건설표준품셈 공통부문
8-2-1 불도저」 참조
「건설표준품셈 공통부문
8-4-3 암성토」 참조
- 859 -
번 호 공 종 단 위 단 가 기 준 비 고
c㎡=T1+T2+T3+T4+T5= 분
Q4=60×5500×0.9/c㎡= 분
13%=Ww/Ws×100%
Ww=1600-Ws
13Ws=100-Ww
13Ws=(1600-Ws)×100
13Ws=160000-100Ws
113Ws=(1600-Ws)×100
Ws=(1600×100)/113=1415.92kg/㎥
W(살수량)=Ws×(0.13-0.08)
=70.80kg/㎥
Q5=Q4/W= ㎥/hr
d-2 필터층 ㎥ 1. 모래 구입 및 운반 : 별도계상
2. 포설
1) 모우터그레이다(3.6m)
W=2.9m, H=0.3m, D=50m
E=0.6, N=4회, f=C/L
V1=6.0, V2=6.5, t=0.5
cm=0.06×(D/V1+D/V2)+2×t= 분
Q=60×W×D×H×E×f/(N×cm)= ㎥/hr
3. 다짐
1) 진동로라 (자주식 10TON)
N=6, V=4, W1=1.9, E=0.6, H=0.3, f=1
Q=1000×V×W1×E×H×f/N= ㎥/hr
2) 타이어로라 (8-15TON)
N=4, V=2.5, W=1.8, E=0.6, H=0.3, f=1
Q=1000×V×W×E×H×f/N= ㎥/hr
「건설표준품셈 공통부문
8-2-7 모터그레이더」 참조
「건설표준품셈 공통부문
8-2-9 롤러」 참조
- 860 -
번 호 공 종 단 위 단 가 기 준 비 고
4. 살수비 (물탱크 5500ℓ)
E4=0.9, L=1.0km, O.M.C=13%,
N.M.C=8%, T1=5분(흡입준비),
T3=10분(흡입시간),
T4=5분(살수대기),
T5=20분(살수시간),
T2=1.0/15×2×60 =8분(운반시간)
c㎡=T1+T2+T3+T4+T5= 분
Q4=60×5500×0.9/c㎡= 분
13%=Ww/Ws×100%
Ww=1600-Ws
13Ws=100-Ww
13Ws=(1600-Ws)×100
13Ws=160000-100Ws
113Ws=(1600-Ws)×100
Ws=(1600×100)/113=1415.92kg/㎥
W(살수량)=Ws×(0.13-0.08)
=70.80kg/㎥
Q5=Q4/W= ㎥/hr
「건설표준품셈 토목부문
6-9-5 하수관 준설(흡입식)」 참
조
d-3 비탈면 흙쌓기 ㎥ 1. 포설 (굴삭기 0.7㎥)
q= 0.7, k=1.1, f=C/L, E=0.7, Cm=20sec
Q=3600×q×k×f×E/Cm= ㎥/hr
2. 다짐 (플레이트콤팩터 1.5TON)
V=1km/h, W=0.45m, E=0.6, N=3회, D=0.1m, f=1
Q=1,000×V×W×E×D×f/N=㎥/hr
「건설표준품셈 공통부문
8-2-3 굴삭기」 참조
「건설표준품셈 공통부문
8-2-10 플레이트 콤팩터」 참조
1.10 뒷채움 및 다짐공 ㎥ ※ 구조물공 4.04 참조
- 861 -
번 호 공 종 단 위 단 가 기 준 비 고
1.11
a
노상준비공
깎기부 ㎡
1. 긁어 일으키기
(도쟈 32TON+립퍼 3본)
H=0.2m, D1=50, E=0.85, f=1.0, Am=0.6,
Cm1=(0.05×D1)+0.25= 분
Q1=((60×Am×D1×E1)/(Cm1×H)= ㎡/hr
2. 노면정리 (그레이다 3.6m)
L=2.9m, D2=50m, E2=0.5, N1=2회, f=1.0
V1=6, V2=6.5, t=0.5분, H=0.2m
C㎡=0.06×(D2/V1+D2/V2)+(2×t)= 분
Q2=(60×L×D2×E2×H/(N1+C㎡×H))= ㎡/hr
3. 다짐
1) 진동로라 (자주식 10TON)
N2=6회, V0=4, W1=1.9, E3=0.6
f=1.0, D3=0.05m, H=0.2m
Q3=(1000×V0×W1×E3×f×D3/(N2×H))= ㎡/hr
2) 타이어로라 (자주식 8-15TON)
N3=1회, V=2.5, W2=1.8, E4=0.6
f=1.0, D4=0.05m, H=0.2m
Q4=(1000×V×W2×E4×f×D4/(N3×H))= ㎡/hr
「건설표준품셈 공통부문
8-2-1 불도저」 참조 「건설표준품셈 공통부문
8-2-2 리퍼」 참조
「건설표준품셈 공통부문
8-2-7 모터그레이더」 참조
「건설표준품셈 공통부문
8-2-9 롤러」 참조
- 862 -
번 호 공 종 단 위 단 가 기 준 비 고
b 기존도로부 ㎡ 1. 도로면 절취 및 정리 (그레이다 3.6m)
L=2.3, D1=50, E1=0.6, N1=2회, f=1.0
V1=6, V2=6.5, t=1.5분, H=0.05m
Cm1=0.06×(D1/V1+D1/V2)+2×t= 분
Q1=(60×L×D1×E1×H)/(N1×Cm1×H)= ㎡/hr
2. 다짐
1) 진동로라 (자주식 10TON)
N2=2회, V0=4, W1=1.9, E2=0.6
f=1.0, D2=0.05m, H=0.05m
Q2=(1000×V0×W1×E2×D2)/(N2×H)= ㎡/hr
2) 타이어로라 (8-15TON)
N3=1회, V=2.5, W2=1.8, E3=0.6
f=1.0, D2=0.05m, H=0.05m
Q3=(1000×V×W2×E3×f×D2)/(N3×H)= ㎡/hr
3. 살수비 (노상살수의 10%)
(물탱크 5500ℓ, L=1.0km) ∙소요살수량 5% : 1415.92kg/㎥×0.05=70.80kg/㎥
t1=5분 (준비), t3=10분 (흡입)
t4=5분 (대기), t5=20분 (살수)
V1=15km/hr, V2=15km/hr
C㎡=40+(1/15×60×2)= 분
Q4=(60×5.5×0.9/(C㎡×0.0708))×0.1= ㎡/hr
「건설표준품셈 공통부문
8-2-7 모터그레이더」 참조
「건설표준품셈 공통부문
8-2-9 롤러」 참조
「건설표준품셈 토목부문
6-9-5 하수관 준설(흡입식)」 참
조
1.12
a
되메우기 및 다짐
(기계 100%)
되메우기 및 다짐 ㎥ 1. 기계(100%) : 굴삭기 1.0㎥
q=1.0, k=0.9, f=0.9/1.3=0.692, E=0.65, cm=19sec(90˚)
Q=(3600×q×k×f×E)/cm=㎥/hr
2. 다짐(램머 80kg)
A=0.28×0.33=㎡, N= 36,000회/hr, H=0.15m,
f=1.0, E=0.5, P=57회
Q=(A×N×H×f×E)/P=㎥/hr
「건설표준품셈 공통부문
8-2-3 굴삭기」 참조 「건설표준품셈 공통부문
8-2-11 래머」 참조
※ 배수공의 L형측구, 부대공의 방
음벽 및 다이크 되메우기량 등에
적용
- 863 -
번 호 공 종 단 위 단 가 기 준 비 고
b 되메우기(비다짐)
㎥
1. 기계(100%) : 굴삭기 1.0㎥
q=1.0, k=0.9, f=1/L, E=0.65, cm= 19sec(90˚)
Q=(3600×q×k×f×E)/cm=㎥/hr
「건설표준품셈 공통부문
8-2-3 굴삭기」 참조
※ 배수공의 L형측구, 부대공의
방음벽 및 다이크 되메우기량 등
에 적용
1.13 쌓기비탈면다짐 ㎡ 1. 법면다짐(유압식 진동 콤펙터+굴삭기 0.7㎥)
A = 77.7 ㎡/hr
「건설표준품셈 공통부문
8-2-17 법면 다짐기」 참조
1.14 층따기 ㎥ 1. 법면 절취 (도쟈 19ton)
L=20m, f=1/1.3, E=0.60
V1=40, V2=46, q=3.2×0.96 =
Cm=L/V1+L/V2+0.25 =
Q=60×q×f×E/Cm = m3/hr
「건설표준품셈 공통부문
8-2-1 불도저」 참조
1.15
a
토공 규준틀설치
비탈규준틀 ea 1. 판재 (t=1.2cm, B=12cm, L=4m)
- 재료비 : (0.012×0.12×4)×0.5 =
2. 말뚝 (말구6cm, L=1.8m 2본)
A=(0.06×0.06)×3.14×1/4×1.8 =
- 재료비 : A×2본×0.5 =
3. 못 (75m/m)
- 재료비 : 0.03kg
4. 목공 : 0.16인
5. 보통인부 : 0.14인
「건설표준품셈 공통부문
2-5 규준틀」 참조
b 수평규준틀 ea 1. 목재 : 0.014m3×0.8 =
2. 못 (75m/m)
- 재료비 : 0.03kg
4. 목공 : 0.21인
5. 보통인부 : 0.19인
「건설표준품셈 공통부문
2-5 규준틀」 참조
- 864 -
번 호 공 종 단 위 단 가 기 준 비 고
1.16
a
연약지반 처리공
침하토 쌓기 및 다짐 ㎥ 1. 흙쌓기 노체다짐 참조
b 샌드매트 부설
(T= 0.5 m)
㎥ 1. 모래구입 : 별도계상
2. 모래운반 : 별도계상
3. 포설 (습지도쟈 13.0 Ton)
D =20m, E=0.70, e=0.96, f=0.9/1.15
V1=55m/분, V2=70m/분, t=0.25m
qo=1.5×e
cm=D/V1+D/V2)+0.25
Q1=60×qo×f×E/cm= m3/hr
4. 살수비 (물탱크 5500ℓ)
E4=0.9, L=1.0km, O.M.C=13%, N.M.C=8%
T1=5분(흡입준비), T3=10분(흡입시간)
T4=5분(살수대기), T5=20분(살수시간)
T2=1.0/15×2×60=8분(운반시간)
cm2=T1+T2+T3+T4+T5= 분
Q4=60×5500×0.9/cm2= 분
Ww=1600-Ws
13Ws=100-Ww
13Ws=(1600-Ws)×100
13Ws=160000-100Ws
113Ws=(1600-Ws)×100
Ws=(1600×100)/113=1415.92kg/m3
W(살수량)=Ws×(0.13-0.08)=70.80kg/m3
Q5=Q4/W= m3/hrWw=1950-Ws
5. 다짐
1) 진동로라 (자주식 10TON)
N2=6, V=4, W1=1.9, E2=0.6
D2=0.25, f=1.0
Q2=1000×V×W1×E2×D2×f/N2= m3/hr
「건설표준품셈 공통부문
8-2-1 불도저」 참조
「건설표준품셈 토목부문
6-9-5 하수관 준설(흡입식)」 참
조
「건설표준품셈 공통부문
8-2-9 롤러」 참조
- 865 -
번 호 공 종 단 위 단 가 기 준 비 고
c P.P매트 부설
(T= 5 Ton/m)
(T= 10 Ton/m)
(T= 15 Ton/m)
㎡ 1. 자재비
P.P매트 : 1.0㎡×1.10
2. 부설비
1) 보통인부 : 0.0007인
2) 특별인부 : 0.0014인
「건설표준품셈 공통부문
5-2-1 매트부설」 참조
d P.E.P매트 부설
(T= 15 Ton/m)
(T= 20 Ton/m)
㎡ 1. 자재비
P.E.P매트 : 1.0㎡×1.10
2. 부설비
1) 보통인부 : 0.0007인
2) 특별인부 : 0.0014인
「건설표준품셈 공통부문
5-2-1매트부설」 참조
e 샌드 드레인
(D 400mm)
m 총연장 : m , 총본수 : 본
평균연장 : 총연장/ 총본수 = m/본
※ 장비조합
- Casing 항타 및 인발
진동파일햄머+무한궤도 크레인+리더+모래말뚝 케이싱+발전기
- Casing내 모래투입 : 페이로더 1.34㎥/hr 타이어
공기압축기
※ 인력편성
보링공 : 1.0인
특별인부 : 1.0인
보통인부 : 1.0인
※ 작업소요시간
T=(T1+T2)/f
T1=2분, T2=L1×t1, t1=0.6분/m, f=0.8
「건설표준품셈 공통부문
5-2-4 모래말뚝」 참조
- 866 -
번 호 공 종 단 위 단 가 기 준 비 고
1. 모래구입 및 운반 : 별산
2. 중기사용료
1) 크레인(무한궤도)
L=20m 이하 50ton 1대
L=20~30m 80ton 1대
2) 진동파일해머
L=20m 이하 90kw 1대
L=20~30m 120kw 1대
3) 리더
L=20m 이하 31m 1대
L=20~30m 36m 1대
4) 모래말뚝 케이싱
L=20m 이하 22m 1대
L=20~30m 27m 1대
5) 공기압축기
L=20m 이하 10.3㎥ 1대
L=20~30m 17.0㎥ 1대
6) 발전기 350kw 1대
7) 로더 1.34㎥ 1대
3. 인건비
보링공 1인, 특별인부 1인, 보통인부 1인
4. 부속장비(스킵버킷, 공기탱크, 자동기록장치 등)의 기계경비 및 소요자재(용접봉, 호스
등) : 노무비의 9%
5. 장비조립 및 해체(회당)
소요일수 : 조립 2일, 해체 1일
기계설비공 1인, 특별인부 2인, 용접공 1인, 크레인 250ton 1대
- 867 -
번 호 공 종 단 위 단 가 기 준 비 고
f 샌드 콤팩션 파일
(D 700mm)
m 총연장 : m , 총본수 : 본
평균연장 : 총연장/ 총본수 = m/본
※ 장비조합
- Casing 항타 및 인발
진동파일햄머+무한궤도 크레인+리더+모래말뚝 케이싱+발전기
- Casing내 모래투입 : 페이로더 1.34㎥/hr 타이어
공기압축기
※ 인력편성
보링공 : 1.0인
특별인부 : 1.0인
보통인부 : 1.0인
※ 작업소요시간
T=(T1+T2)/f
T1=2분, T2=L1×t1, t1=0.6분/m, f=0.8
1. 모래구입 및 운반 : 별산
2. 중기사용료
1) 크레인(무한궤도)
L=20m 이하 50ton 1대
L=20~30m 80ton 1대
2) 진동파일해머
L=20m 이하 90kw 1대
L=20~30m 120kw 1대
3) 리더
L=20m 이하 31m 1대
L=20~30m 36m 1대
「건설표준품셈 공통부문
5-2-4 모래말뚝」 참조
- 868 -
번 호 공 종 단 위 단 가 기 준 비 고
4) 모래말뚝 케이싱
L=20m 이하 22m 1대
L=20~30m 27m 1대
5) 공기압축기
L=20m 이하 10.3㎥ 1대
L=20~30m 17.0㎥ 1대
6) 발전기 350kw 1대
7) 로더 1.34㎥ 1대
3. 인건비
보링공 1인, 특별인부 1인, 보통인부 1인
4. 부속장비(스킵버킷, 공기탱크, 자동기록장치 등)의 기계경비 및 소요자재(용접봉, 호스
등) : 노무비의 9%
5. 장비조립 및 해체(회당)
소요일수 : 조립 2일, 해체 1일
기계설비공 1인, 특별인부 2인, 용접공 1인, 크레인 250ton 1대
g 팩 드레인
(D 120mm)
m ※ Casing 제작
총연장: m , 총본수: 본
평균연장: 총연장/ 총본수= m/본
※ 장비조합
- Casing 항타 및 인발
무한궤도 크레인50Ton+진동파일햄머90KW+발전기350KW+리더31M+케이싱
22M+Skip Buckt10㎥+자동기록장치+Hopper1.0
- Casing내 모래투입
Air Compressor(17.0㎥/min 365CFM)+Air Hose(3/4")
- 작업조편성
작업반장:1.0인 비 계 공:1.0인 용 접 공:1.0인
특별인부:4.0인 보통인부:2.0인
- 869 -
번 호 공 종 단 위 단 가 기 준 비 고
※ Pack Drain 시공능력
Q=60*L*E/CM , L=타설길이(M) , E=(0.6+0.8)/2=0.70
T1=140 sec , T3=130 sec , T4=220 sec , T2=L/(0.08+0.05/2)= sec ,
T5=L/0.08= sec,
CM=T1+T2+T3+T4+T5= sec , Q1=(3600*L*0.7/CM)*4= M/HR
1. Casing 항타 및 인발
1) 크레인(무한궤도)50Ton
2) 진동파일햄머(90KW)
2. 재료비
1) Pack Drain:1.0m
2) 안내판:15.70 EA
3. 모래구입
4. 모래운반
5. Pack내 모래투입
1)페이로다(타이어)1.72㎥
Q1=1.72 , K=1.2 , F=0.78 , E=0.75
CM=1.8+8+6+14=29.80분, Q2=3600*Q1*K*F*E/CM=㎥/HR
(P.D 1본당 속채움모래량:외경 D=120m/m*4EA)
V=(3.14*(0.12**2)/4)*4=0.045㎥/m * 1.2(할증)=0.054㎥/m * L= ㎥/m
6. Air Compressor(10.3㎥/min 365CFM)
7. 발전기(350KW)
8. Air Hose(3/4")
9. 인력품
작업반장:1.0인, 비 계 공:1.0인, 용 접 공:1.0인,
특별인부:4.0인, 보통인부:2.0인
10. 자동기록장치 사용료:손료계상
11. Leader(31M):손료계상
- 870 -
번 호 공 종 단 위 단 가 기 준 비 고
12. Casing(22M):손료계상
13. Skip Bucket(10㎥):손료계상
14. Hopper(3.2㎥):손료계상
h 표토제거 ㎡ 1. 습지도쟈(13.0 Ton)
D=20.0m, E=0.4, e=0.96, f=1/1.3
V1=40m/분, V2=48m/분 , T=0.2 m
q0=1.5×e=
cm=D/V1+D/V2+0.25=
Q1=60×q0×f×E/cm= m3/hr
Q=Q1/T= m2/hr
「건설표준품셈 공통부문
8-2-1 불도저」 참조
i 과재쌓기 ㎥ 1. 포설 (모터그레이더 3.6m)
L=2.9m, H=0.3m, D1=50
E1=0.6, N1=4회, f=1.0
V1=6, V2=6.5, t=0.5
cm1=0.06×(D1/V1+D1/V2)+(2×t)= 분
Q1=60×L×D1×H×E×f/(N1×cm1)= m3/hr
「건설표준품셈 공통부문
8-2-7 모터그레이더」 참조
j 과재쌓기제거 ㎥ 1. 도 쟈(32.0 Ton)
D=20.0m, E=0.6, h=0.96, f=1/1.3
V1=40m/분, V2=43m/분 , T=0.2 m
q0=5.5×h=
cm=D/V1+D/V2+0.25=
Q1=60×q0×f×E/cm= ㎥/hr
2. 적 재 (로우더 2.87㎥ 타이어)
q0=2.87, K=1.2, f=1/1.3, E0=0.6
m=1.8, L=8m, t1=9, t2=14
cm=(m×L)+t1+t2= sec
Q1=3600×q0×K×f×E0/cm= ㎥/hr
3. 운 반 (덤프 15TON)
L= km, E=0.9, f=1/1.3
q1=15/1.6ton/m3×1.3=
n= q1 (2.87×k) = 회
T1=(cm×n)/(60×E0)= 분
T2=(L/15+L/20)×60= 분
T3=1.5, T4=0.7, T5=0.5, T6=1.5
cm=T1+T2+T3+T4+T5= 분
Q=60×q1×f×E/cm= m3/hr
「건설표준품셈 공통부문
8-2-1 불도저」 참조 「건설표준품셈 공통부문
8-2-5 로더」 참조 「건설표준품셈 공통부문
8-2-8 덤프트럭」 참조
※ 세륜기 통과 시에만 T6 적용
- 871 -
번 호 공 종 단 위 단 가 기 준 비 고
k 치환토 ㎥ 1. 습지도쟈(13 Ton)
D=20.0m, E=0.55, e=0.96, f=1/1.3
V1=40m/분, V2=48m/분
q0=1.5×e=
cm=D/V1+D/V2+0.25=
Q1=60×q0×f×E/cm= m3/hr
「건설표준품셈 공통부문
8-2-1 불도저」 참조
l 침하판 ea 1. 1인치 Pipe
1)철판(0.9*0.9*0.1) : 63.59 kg
2)강관(D=1") : 1.0m
3)고철
4)용접비(fillet용접 T=5m/m) : 0.107m(외경0.034*3.14)
2. 지지발이붙은 D=150m/m pipe
1)강관(D=150m/m) : 1.0m
2)원형봉강(D=16m/m , L=120cm 3EA) :
1.58kg*1.2m*3EA
3)Steel Plate(D=250 T=4m/m 3EA) :
1.54kg*3EA
4)고철
5)용접비(fillet용접 T=5m/m) : 0.9m
m 침하측정봉 및 보호관 m 1. 침하측정봉 및 보호관
1)1인치 Pipe : 1.0m
2)연결장치 : 재료비의 20%
2. 침하봉보호관(D=150m/m)
1)강관(D=150m/m) : 1.0m
2)연결장치 : 재료비의 20%
- 872 -
번 호 공 종 단 위 단 가 기 준 비 고
n 계측설치비 ea 1. 계측기
1) 기계손료: 개월
2. 재료비
평균심도(H)= m, 지 지 층(H1)= m, 상단여유고(H2)= m
D=H+H1+H2= m
1) ABS 수지 Casing(3m):4EA
2) ABS 수지 Casing Coupling:3EA
3) Rutter End Cap:2EA
4) 보호관:1EA
5) Sealing Type:1EA
3. 천공비
1) 소운반(리어카운반)
V=2000m/hr , T=5 min
N=(2000*450)/(120*200+2000*5)=26.47 회
Q=26.47*250/1000=6.62 ton
소요인수:N=3 ton/Q=0.45인
2) 기계기구설치
중급기술자:1.0인
초급기술자:1.0인
중급기능사:1.0인
3) 보링비(점토층)
천공길이:D1=H+H1= m
중급기술자:0.175인
보 링 공:0.350인
특수인부:0.350인
보통인부:0.350인
- 873 -
번 호 공 종 단 위 단 가 기 준 비 고
코아튜브:0.01EA
메탈크라운:0.025EA
드라이브파이프헤드:0.01EA
드라이브파이프슈:0.01EA
드라이브파이프:0.01EA
경유:2.132ℓ
잡유:0.2ℓ
4)기계기구손료:1.333hr
4. 계측 인력품
건설기술관리법시행령 제91조(품질시험 및 검사) 및 동법 시행규칙 제50조(품질시험 및 검
사의 실시)의 규정에 따라 건설업자는 품질시험 및 검사에 필요한 검사장비와 시험검사요원
을 건설공사의 공정에 따라 배치하여야 하고, 이에 소요되는 비용은 간접노무비에 포함되어
있으므로 계측을 위하여는 이에 필요한 측정용 기기설치에 따른 비용을 제외하고는 별도의
노무비를 계상하지 않는 것으로 한다.
5.계측분석비(조사)
∙분석인원
※ 간극수압계 분석비
- 특급기술자 A1=0.015인
- 고급기술자 B1=0.030인
- 중급기술자 C1=0.035인
※ 경사계 분석비
- 특급기술자 A2=0.020인
- 고급기술자 B2=0.040인
- 중급기술자 C2=0.050인
※ 변위말뚝 측정계 분석비
- 특급기술자 A3=0.010인
- 고급기술자 B3=0.020인
- 중급기술자 C3=0.025인
- 874 -
번 호 공 종 단 위 단 가 기 준 비 고
※ 지표침하판 분석비
- 특급기술자 A4=0.005인
- 고급기술자 B4=0.010인
- 중급기술자 C4=0.010인
1.17 자재운반비
a 모래 운반 m3 1. 구 입 : 별도계상
2. 운 반(덤프 15ton 80% + 덤프 24ton 20% )
Q= 60×qt×f×E/Cm
1.18
a
사급 자재대
모 래(상차도) m3 재료비 : 시중 물가지 참고